Auxiliary service board start-up
(Optional)
This section describes the procedure to start-up the auxiliary service board.
See also, electrical diagrams of the AC cabinet 3AES-PVS980-CS-4600-14-SP01 delivered
with the unit.
Additional information
Task
Set the position of the 98A1 switch to ON position
(AC distribution cubicle).
Check that the MV transformer is de-energized
(open).
Connect the Auxiliary service board.
Check that all switches, disconnectors and
breakers of the Auxiliary service board are open.
Close the main switch of the Auxiliary service
transformer.
Energize the MV transformer.
Voltage level depends on the inverter type:
600 / 630 / 660 / 690 V
Check that the incoming voltage level is equal to
inverter voltage AC output.
Close Auxiliary service transformer primary
breaker.
Check that voltage is 400 /230 V +/-10%.
Check that the Auxiliary service transformer sec-
ondary winding voltage level is 400 / 230 V.
Close Auxiliary service transformer secondary
breaker.
Check that there is no voltage before opening the
next auxiliary breaker.
Close the auxiliary breakers one at a time. and
check the voltage of each breaker.
Also check that the auxiliary service lines with
load are closed. Only switches/breaker with load
should be open.
9