Additional information
Task
Close the AC disconnector [Q2] of the first inverter
[PVS1] to be commissioned.
Step away and out of inverter equipment room or
container to wait inverter's first start. This can be
done by setting start-up delay to inverter paramet-
ers.
See
PVS800-57B hardware manual
(3AXD50000048300 [English]).
Perform the rest of the inverter commissioning
tasks (if any).
Close the AC disconnector [Q2] of the second in-
verter [PVS2] to be commissioned.
Repeat the commissioning tasks (if any) for the
second inverter.