
Storing, lifting and transporting 25
Lifting the inverter in the shipping package
With a crane
•
Lift the inverter in its shipping packaging. If you remove the packaging, protect the
inverter from scratches and dents.
•
Make sure that the slings have sufficient loading capacity.
•
The minimum length of each sling is 1.8 m.
•
Adjust the lengths of the lifting slings to make sure that the inverter does not tilt.
•
Attach a guide wire to a bottom corner of the inverter to prevent rotation.
max 20
Position each sling as
close to a transverse
board as possible.
We recommend the use
of transverse spreader
bars.
Lifting point
Содержание PVS800-57B
Страница 1: ...ABB SOLAR INVERTERS PVS800 57B central inverters Commissioning and maintenance manual...
Страница 4: ......
Страница 8: ...8...
Страница 16: ...16 Safety instructions...
Страница 22: ...22 Introduction to the manual...
Страница 27: ...Storing lifting and transporting 27 Moving the crate with a forklift...
Страница 38: ...38 Mechanical installation...
Страница 50: ...50 Electrical installation...
Страница 56: ...56 Start up and operation...
Страница 70: ...70 Maintenance 5 6 4 3...
Страница 71: ...Maintenance 71 7 8 8...
Страница 72: ...72 Maintenance 9 10...
Страница 76: ...76 Maintenance...