EntelliGuard R Circuit Breaker Retrofill AKD-6 Installation Manual DEH-41548 07/15
Remove and Replace Existing Door
It must be ensured that the supply power to
the compartment is turned off/ compartment
is de-energized for all the incoming and outgoing
circuits of the LVS prior to any work being
conducted on it.
During the installation and related work on the
equipment, it must be ensured that the operator is
using the prescribed PPE for the specified tasks.
Ensure only qualified personnel install, operate, service, and maintain all electrical equipment.
1.
To remove existing compartment door(s), refer to your manual on how to remove the legacy doors.
2.
To install new door, refer to the
Retrofill Door Assemblies, DEH-41563
.
Prepare Switchgear Compartment
Ensure the circuit breaker has been tripped,
indicating OFF, and the main springs are fully
discharged.
Do not touch the circuit breaker’s isolating
contacts during lifting
Failure to comply with these instructions could
result in death or serious injury
.
Ensure only qualified personnel install, operate, service, and maintain all electrical equipment.
1.
Before modifying the switchgear compartment, de-energize/switch off the breaker. If the circuit breaker is
ON and the springs are charged, to turn it off, press the OPEN button on the circuit breaker fascia, and ensure
that the circuit breaker contacts are open.
2.
Inspect the compartment for damage, rework (
).