28
Optional Equipment Procedures
If Modulating Hot Gas Reheat is equipped,
additional installation steps are required.
1. Field installed piping is required.
2. The field supplied thermostat and
humidistat must be wired to the reheat
control as shown in the unit wiring diagram.
3. Verify that the condenser hot gas valve
and reheat hot gas valve are wired as shown
in the wiring diagram.
4. Verify that the Modulating Hot Gas
Reheat system is working properly. Run for
five minutes in the reheat mode and verify
that the temperature of the supply air stream
matches the reheat temperature set point.
Commissioning
Air Balancing
High performance systems commonly have
complex air distribution and fan systems.
Unqualified personnel should not attempt to
adjust fan operation, or air circulation, as all
systems
have
unique
operating
characteristics. Professional air balance
specialists should be employed to establish
actual operating conditions, and to configure
the air delivery system for optimal
performance.
Water Balancing
A hydronic specialist with a complete
working knowledge of water systems,
controls and operation must be employed to
properly
balance
the
entire
system.
Unqualified personnel should not attempt to
manipulate temperatures, pressures, or flow
rates, as all systems have unique operating
characteristics, and improper balancing can
result in undesirable noises and operation.
Controls
A variety of controls and electrical
accessories may be provided with the
equipment.
Identify the controls on each unit by
consulting appropriate submittal or order
documents, and operate according to the
control manufacturer’s instructions. If you
cannot locate installation, operation or
maintenance information for the specific
controls,
then
contact
your
sales
representative, or the control manufacturer
for assistance.
Operation and Maintenance
General
Immediately following unit startup, the air
conditioning system requires a maintenance
schedule to assure continued successful
operation. A maintenance program similar to
the example given below should be
scheduled for routine maintenance of this
equipment in order to provide efficient and
reliable operation for the owner.
Maintenance Schedule
One week after start-up:
Check refrigerant charge. Evacuate and
repair if leaking.
Check filters for cleanliness. Measure
pressure loss if applicable. Replace if
necessary.
Check cycling of compressors, fans and
valves. Correct unusual cycling.
Monthly:
Check cleanliness of filters, and replace if
necessary.
Check cooling coil drain pan to assure
proper drainage or correct.
Inspect evaporator and condenser coils.
Clean if dirty or obstructed in any way.
Содержание F1-060
Страница 31: ...31 ...
Страница 33: ...33 Figure 5 Modulating Hot Gas Reheat Piping Diagram with Air Handling Unit below Condensing Unit ...
Страница 36: ...36 Figure 8 Heat Pump Piping Diagram with Indoor Unit above Outdoor Unit ...
Страница 37: ...37 Figure 9 Heat Pump Piping Diagram with Outdoor Unit above Indoor Unit ...
Страница 38: ...38 Figure 10 Heat Pump Piping Diagram with Modulating Hot Gas Reheat and Indoor Unit above Outdoor Unit ...
Страница 39: ...39 Figure 11 Heat Pump Piping with Modulating Hot Gas Reheat and Outdoor Unit above Indoor Unit ...
Страница 40: ...40 Thermostat Installation and Wiring Figure 12 2 Stage Cooling with Electric Heat ...
Страница 41: ...41 Figure 13 2 Stage Cooling with Heat Pump and Electric Heat ...
Страница 42: ...42 Figure 14 2 Stage Cooling and Electric Heat with Hot Gas Reheat and Humidistat ...
Страница 43: ...43 Figure 15 Main Control Board for Units Equipped with Modulating Hot Gas Reheat ...
Страница 45: ...45 Figure 17 5kW Electric Heat ...
Страница 46: ...46 Figure 18 10 kW Electric Heat ...
Страница 47: ...47 Figure 19 15 kW Electric Heat ...
Страница 48: ...48 Figure 20 20 kW Electric Heat ...
Страница 49: ...49 Figure 21 25 kW Electric Heat ...
Страница 55: ...55 ...