Configuring the Controller
Configuration
Binary Input #4
In this example this is the input configuration screen for “Boiler POF”
on Binary Input #4 (BIN4). Item #1 in
Figure 20
indicates the Boiler
Proof Of Flow binary input is configured for a normally open contact.
In this configuration the flow switch associated with the boiler water
pump would activate this contact insuring that water flow exists in the
boiler water piping.
Binary Input #5
In this example this is the input configuration screen for “Boiler Alarm”
on Binary Input #5 (BIN5). Item #1 in
Figure 21
indicates the “Boiler
Alarm binary input is configured for a normally open contact. In this
configuration an alarm contact from the boiler protection control (by
others) would close to activate this alarm contact. In this case it is shown
as a normally open contact.
Binary Input #6
In
Figure 22
Item #1 it indicates that Binary Input #6 (BIN6) is not used
in this typical configuration. Your application may require its use and it
can be configured as needed.
Figure 22: BIN6 Input Screen
1
23