Figure 3-2 Single machine installation space requirement (200kW-355kW)
For the double machine parallel installation, please refer to Table 3-3 and Figure 3-3 to reserve
the space between the frequency converters.
Figure 3-3 Double machine parallel installation diagram
Table 3-3 Double machine parallel installation space requirement (2.2kW-160kW)
Power Level (kW)
Parallel Installation Space Requirement A (mm)
2.2-22
≥10
30-37
≥50
45-55
≥50
75-110
≥50
132-160
≥50