25
12-OPERATION
12.1 Operator's Correct Working Position and
Operational Flow (Figure 12-1).
Once the box has been
fi
lled, close its top
fl
aps and
push it between the top and bottom drive belts.
Always keep hands in position as shown in
Figure 12-2.
The box will be automatically sealed with
adhesive tape on the top and bottom box seams.
Then the box will be expelled on the exit conveyor.
12.4 Tape Replacement and Threading
See Manual 2: AccuGlide™ 2+ STD 2 Inch
Taping Heads.
Press the
LATCHING EMERGENCY STOP BUTTON.
12.5 Box Size Adjustment
Repeat all the operations shown in
Section 11 - Setup and Adjustments.
12.6 Cleaning
Before carrying out any cleaning or maintenance
operation stop the machine by turning the OFF
rotary switch on the main and disconnect the electric
power
(Figure 12-3).
12.8 Safety Devices Inspection
1 Taping units blade guard
2 Latching emergency stop button
3 STOP (OFF) main rotary switch
Operator Qualif
i
cations
1 Tape loading and threading
1
2 Tape web alignment
1
3 Adjustment of one way tension roller
1
4 Adjustment to box size (H and W)
1
5 Top
fl
ap compression rollers
1
6 Adjustment of tape applying spring
1
7 Conveyor bed height adjustment
1
8 Special Adjustment-Changing tape leg length 2
9 Special Adjustment-Column re-positioning
2
12.7 Table of Operation Adjustments -
12.2 Starting the Machine
Important:
Before starting the machine, verify that
no tools or other objects are on the conveyor bed.
Turn the main rotary switch ON after the
EMERGENCY BUTTON is released
(Figure 12-3).
12.3 Starting Production
After having adjusted the machine according to
the box dimensions (height-width), let the machine
run without cartons and check its safety devices.
Then start the working cycle.
Figure 12-1
2011 April
a20-NA
Figure 12-1
Hand
Position
Figure 12-2
Figure 12-3
Содержание 3M-Matic a20
Страница 4: ...THIS PAGE IS BLANK...
Страница 6: ...6 THIS PAGE IS BLANK...
Страница 8: ...THIS PAGE IS BLANK...
Страница 42: ...32 THIS PAGE IS BLANK...
Страница 44: ...34 THIS PAGE IS BLANK...
Страница 45: ...35 16 TECHNICAL DIAGRAMS 16 1 Electric Diagram 1 Phase 2011 April a20 NA...
Страница 46: ...36 THIS PAGE IS BLANK...
Страница 48: ...38 THIS PAGE IS BLANK...
Страница 50: ...40 THIS PAGE IS BLANK...
Страница 60: ...50 2011 April a20 NA 9 13 2 11 12 10 11 7 5 6 7 3 8 4 1 Figure 10673 a20 Adjustable Case Sealer...
Страница 66: ...56 43 41 42 40 37 42 39 38 41 36 35 34 35 36 2011 April a20 NA Figure 10676 2 a20 Adjustable Case Sealer...
Страница 70: ...60 THIS PAGE IS BLANK...
Страница 72: ......
Страница 74: ...THIS PAGE IS BLANK...
Страница 76: ...THIS PAGE IS BLANK...
Страница 80: ...2 THIS PAGE IS BLANK...
Страница 104: ...26 STD 2 Taping Head NA 2011 1RYHPEHU Figure 10387 Upper Head 9 9 9 1 9 4 5 3 8 7 9 9 2 9 10 11 AccuGlide 2 STD 2 Inch...
Страница 106: ...28 Figure 10395 Upper and Lower Heads STD 2 Taping Head NA 2011 1RYHPEHU 2 6 6 3 1 4 5 3 5 4 AccuGlide 2 STD 2 Inch...
Страница 112: ...34 Figure 10399 Lower Head 2 STD 2 Taping Head NA 2011 1RYHPEHU AccuGlide 2 STD 2 Inch...
Страница 114: ...36 Figure 10389 Lower Head STD 2 Taping Head NA 2011 1RYHPEHU 9 11 7 2 3 8 5 4 1 9 9 10 9 9 9 AccuGlide 2 STD 2 Inch...
Страница 116: ...38 THIS PAGE IS BLANK...
Страница 117: ...39...
Страница 118: ...40...