FLOOR DRAIN INSTALLATION INSTRUCTIONS
Zurn Industries, LLC
|
Specification Drainage Operation
1801 Pittsburgh Avenue, Erie, PA U.S.A. 16502 · Ph. 855-663-9876, Fax 814-454-7929
In Canada
|
Zurn Industries Limited
3544 Nashua Drive, Mississauga, Ontario L4V 1L2 · Ph. 905-405-8272, Fax 905-405-1292
www.zurn.com
Rev.
C
Date:
02/27/2018
C.N. No.
139680
Form No. FD97
Page
6 of 6
®
For Correcting a Tilted Drain (Steps 15, 16 and
17)
15. Remove strainer and strainer frame from installed head
assembly.
See Fig. 15
16. A shim set and longer screws are included under the label
of the rough-in cover.
Install shims on shank and adjust/rotate shims as needed
to bring strainer level with the finished floor. (Included
shims can adjust for up to 1/4" [6 mm] of tilt. See Fig. 16
17. Reinstall strainer frame and strainer. Use included longer
screws as needed. Torque screws to 16-18 in-lbs [18.5-
20.5 cm-kg]
Remove protective label from strainer once construction is
complete. See Fig. 17a for Slab on Grade Installation and
Fig. 17b for tile installation