background image

EZ1

TM

 DRAINAGE SERIES

EZ1

TM

 FLOOR DRAIN INSTALLATION INSTRUCTIONS

Zurn  Industries,  LLC

 

|

 

Specification  Drainage  Operation

1801 Pittsburgh Avenue, Erie, PA  U.S.A. 16502 · Ph. 855-663-9876, Fax 814-454-7929
In  Canada

 

|

 

Zurn  Industries  Limited

3544 Nashua Drive, Mississauga, Ontario L4V 1L2 · Ph. 905-405-8272, Fax 905-405-1292

www.zurn.com

Rev.

C

Date:

02/27/2018

C.N. No.

139680

Form  No. FD97

 Page

  6 of 6

®

For Correcting a Tilted Drain (Steps 15, 16 and

17)

15. Remove strainer and strainer frame from installed head

assembly.

See Fig. 15

16. A shim set and longer screws are included under the label

of the rough-in cover.

Install shims on shank and adjust/rotate shims as needed
to bring strainer level with the finished floor.  (Included
shims can adjust for up to 1/4" [6 mm] of tilt. See Fig. 16

17. Reinstall strainer frame and strainer. Use included longer

screws as needed.  Torque screws to 16-18 in-lbs [18.5-
20.5 cm-kg]

Remove protective label from strainer once construction is
complete. See Fig. 17a for Slab on Grade Installation and
Fig. 17b for tile installation

Fig. 15

Fig. 16

Fig. 17b

Fig. 17a

Summary of Contents for EZ1

Page 1: ...mittal for dimensional heights Ensure pipe is cut square and free of burrs or debris See Fig 1 2 Install drain body on pipe and pressure test connection per local code requirements See Fig 2 Neo loc body shown for reference Note All plastic bodies to be solvent welded to pipe 3 Pour the rough floor slab flush with the top of the drain body See Fig 3 Fig 2 Fig 3 Warning Flying material can cause ey...

Page 2: ...structions See Fig 4 Secure the clamp collar to the body with the supplied 3 8 16 x 3 4 hex washer head cap screw Do not overtighten Max torque 8 ft lbs 11 Nm Note Clamp collar can be inverted for a lower rough in height 5 Install rough in cover assembly into clamp collar Adjust rough in cover assembly so the top of the rough in cover is at the finish floor grade See Fig 5 Note Ensure rough in cov...

Page 3: ...r until a visible crack forms around the entire circumference of the rough in cover Rough in cover should appear loose separtates up from concrete See Fig 7 Note Be careful to not hit the finished concrete floor as it will chip damage the finish Only hit the plastic rough in cover Do not use excessive force 8 Break the protective label in the center of the rough in cover to expose a slot See Fig 8...

Page 4: ...ilted See Step 15 Round 11a Place a bead of silicone around the circumference of the last thread of the head assembly See Fig 11R 11b Thread head assembly down until bottom of the frame is flush with the top of the concrete See Fig 11R 11c Place a bead of silicone around the perimeter of the strainer frame See Fig 11R 12 Turn head assembly clockwise until top of strainer is flush with the finish f...

Page 5: ...xture is tilted See Step 15 Round 13 Adjust head assembly to the height of the finished floor See Fig 13R 14 Install finish flooring per manufacturers instructions Remove protective label from strainer once construction is complete See Fig 14R Square 13a Adjust head assembly to the height of the finished floor See Fig 13S 13b Fill in shroud with cement or grout Ensure to completely fill in around ...

Page 6: ... 15 Remove strainer and strainer frame from installed head assembly See Fig 15 16 A shim set and longer screws are included under the label of therough in cover Install shims on shank and adjust rotate shims as needed to bring strainer level with the finished floor Included shims can adjust for up to 1 4 6 mm of tilt See Fig 16 17 Reinstall strainer frame and strainer Use included longer screws as...

Reviews: