![Zte ZXSDR BS8800 C200 Installation Manual Download Page 85](http://html1.mh-extra.com/html/zte/zxsdr-bs8800-c200/zxsdr-bs8800-c200_installation-manual_940276085.webp)
Chapter 7 Installing GPS Antenna Feeder System
Steps
1. Make sure the grounding position of 1/4" GPS feeder; strip a
section of the sheath of GPS feeder (about 25mm) according to
the size of grounding kit, and place the grounding kit through
the stripped position of GPS feeder.
2. Fasten the ground terminal (on the side of grounding kit, with
two grounding holes) onto the grounding kit with M6 hexagon
head screws, place the attached spring washer and plain
washer between screw and ground terminal, and screw down
the screw with a M6 screwdriver.
3. Fasten the other ground terminal (on the side of cooper ground
bar) onto the cooper ground bar with the M8×25 hexagon head
screw, and place the plain washer and spring washer between
screw and copper ground bar.
4. Cover a layer of tung oil on the exposed metal surface.
E
ND OF STEPS
.
Leading GPS Feeder into Room
Context
This step is adoptable for an indoor BTS. While installing the feeder
for an outdoor BTS, the step is no need.
Through a feeder hermetic window, lead the GPS feeder into the
equipment room. Detailed steps refer to
.
Confidential and Proprietary Information of ZTE CORPORATION
77
Summary of Contents for ZXSDR BS8800 C200
Page 6: ...List of Glossary 159 ...
Page 9: ......