Boom Installation
5.3
5.3.1
Boom Installation Procedure
1.
Pull the secondary boom out from the upper boom, and then fasten with 2 screws,
as shown in Figure 1.
2.
The procedure of installing the boom to the chassis is shown in Figure 2.
Note:
1.
Before the barrier is powered on to run the test process, be sure to install the
barrier boom of the corresponding length for the test. If the barrier boom is not
installed, please adjust and remove the spring under the guidance of a
professional.
2.
If the length of the barrier boom is cut and adjusted, the tightness of the spring
and the position of the hanging hole need to be adjusted accordingly to avoid the
abnormal working status that cannot drop the boom.
Figure 1 Connect the main boom with the Secondary arm together by 2 screws
Figure 2 Install the Boom to the Chassis