Zip VP303 Installation, Maintenance And User Instructions Download Page 10

4. An isolating valve (not supplied) must be fitted in the cold water supply

pipework to the inlet manifold assembly to enable isolation of the water
supply to the unit for servicing or replacement.

5. Fit the inlet manifold assembly to the 22mm supply pipework with the valve 

caps facing upwards and in the correct direction of flow as indicated by
the arrows.

6. The pressure gauge connection point on the manifold assembly should be

accessible for connection of a pressure gauge if necessary.

7. Provide suitable drainage from the Expansion Relief and Temperature &

Pressure Relief Valves via the tundish using 15mm copper tube. Refer to
installation requirements.

8. Connect the expansion vessel to the manifold assembly using 15mm

copper tube.

9. A balanced mains pressure cold water supply for a shower may be

provided from the connection provided on the manifold assembly,
otherwise this should be blanked. 

10. Flush all pipework thoroughly before making the final connections from the

cold supply to the manifold assembly to ensure that any debris is removed.
Failure to do this may result in irreparable damage to the controls and will
invalidate the warranty.

11. Connect the hot water supply pipe to the outlet from the heater.

12. Connect the discharge pipe from the tundish. Refer to Installation

Requirements on page 6 and Typical Installation drawing on page 5.

Electrical

Switch off the mains electrical supply before removing the electrical cover panel
or carrying out any work involving a live circuit or access to components that
may be live.

Do not switch on the electrical supply until the unit is full of water.

This appliance must be earthed.

The electrical connection to the heating elements must conform to current IEE
wiring regulations and be permanently connected to the electrical supply
through a double-pole isolating switch with at least 3mm contact separation in
each pole and with a minimum rating of 13A.

All internal wiring is factory mounted and should not be altered or modified. 

After removing the electrical cover panel, a suitable supply cable should be fed
through the cable clamp on the underside of the appliance, connected to the
live and neutral connections on the terminal block and earth terminal on the
element plate before securing with the cable clamp.

Check all electrical connections for security and tightness before replacing the
electrical cover panel.

Zip Varipoint III Installation, Maintenance and User Instructions - August 2008    

11

Varipoint qxd:Varipoint qxd  22/8/08  11:09  Page 9

Summary of Contents for VP303

Page 1: ...mencing installation of the Varipoint unvented water heater Please leave these instructions with the end user after installation Zip Heaters UK Ltd 14 Bertie Ward Way Dereham Norfolk NR19 1TE Telephon...

Page 2: ...a current Registered Operative Identity card for the installation of unvented domestic hot water storage systems issued by an accredited body The Zip Varipoint must be installed in accordance with the...

Page 3: ...External expansion vessel pre charged to 3 5 bar Expansion vessel capacity 5 litre 30 and 50L Varipoint 8 litre 80 and 100L Varipoint Approvals Zip Varipoint III complies with the LVD and EMC directi...

Page 4: ...water supply To drain via tundish Hot water outlet 1 2 9 3 4 5 6 7 8 1 Temperature and pressure relief valve 2 Combined pressure reducing valve and strainer 3 Expansion relief and check valve 4 Balanc...

Page 5: ...the weather These instructions must be read and fully understood before commencing the installation If in doubt or in need of further guidance please ring Zip on 0845 602 4533 Installation must only b...

Page 6: ...perature and pressure relief valves should drain via a tundish which should be installed in a visible location and away from any electrical devices The discharge pipe from the tundish should terminate...

Page 7: ...rge pipe should be at least one pipe size larger than the largest individual discharge pipe to be connected If unvented hot water storage systems are installed where discharges from safety devices may...

Page 8: ...duct Ensure that the wall where the unit is to be located is sufficiently strong to support the full weight of the unit see dimensions and capable of accepting suitable fixings Position the Zip Varipo...

Page 9: ...board or any concealed location For guidance please ring Zip Heaters on 0845 602 4533 Plumbing 1 The unit should be provided with a cold water supply via 22mm pipework 2 The water connections are at t...

Page 10: ...Connect the hot water supply pipe to the outlet from the heater 12 Connect the discharge pipe from the tundish Refer to Installation Requirements on page 6 and Typical Installation drawing on page 5...

Page 11: ...open until all air has been purged from the system and water is flowing freely from all outlets 8 Check for leaks and rectify as necessary 9 Check the operation of both the T P relief valve and the E...

Page 12: ...the electrical supply to the unit isolate the water supply and contact a competent person familiar with unvented systems 9 Please note that lime scale deposits form more readily at higher temperatures...

Page 13: ...n discharge ceases Replace thermostat if faulty Continuous water Pressure reducing valve Check with pressure gauge and discharge from not operating correctly replace as necessary the tundish P T relie...

Page 14: ...and allow the unit to drain De Installation To de install the heater 1 Switch off and disconnect the electrical supply 2 Close the mains water supply isolating valve 3 Drain the heater as described i...

Page 15: ...moval cartage and re installation of any component of the appliance if it needs to be returned for repair to Zip or its Distributor This warranty does not cover damage resulting from non operation of...

Reviews: