Installation and operating instructions V00 23
5.4 AC connection
5.4.1 Conditions for the AC connection
Cable Requirements
The grid connection is established using five conductors (L1, L2, L3, N, and PE).
We recommend the following specifications for copper wire.
No.
Description
Value
A
External diameter
19…28 mm
B
Conductor cross-sectional area
10…25mm
2
C
Stripping length of the insulated conductors
16 mm
D
Stripping length of the cable’s outer sheath
Maximum. 80 mm
The PE insulated conductor must be at least 5 mm longer than the L and N
conductors
Notes: Larger cross-sections should be used for longer cables.
Danger to life due to high voltages in the inverter!
• Before establishing the electrical connection, ensure that the AC
circuit-breaker is switched off.