Commissioning Certificate
Certificate of COMMISSIONING for the Simplicity Plus Fire Alarm System installed at:
ADDRESS:
I/we being the competent person(s) responsible (as indicated by my/our signatures below) for the
commissioning of the fire alarm system, particulars of which are set out below, CERTIFY that the said work
for which I/we have been responsible complies to the best of my/our knowledge and belief with the
recommendations of BS5839-1, except for the variations, if any, stated in this certificate
Name (
Block Letters
):
Position:
Signature:
Date:
For & on behalf of:
Address
The extent of liability of the signatory is limited to the system described below.
Extent of the installation work covered by this certificate.
Variations from the recommendations of BS 5839-1
All equipment operates correctly
Installation work is, as far as can be reasonably ascertained, of an acceptable standard
The entire system has been inspected and tested in accordance with the recommendations of BS 5839-1.
The system performs as required by the specifications prepared by:
Taking into account the guidance contained in BS 5839-1, I/we have not identified any obvious potential
for an unacceptable rate of false alarms.
The documentation described in BS 5839-1 has been provided to the user
The following work should be completed before/after (delete as applicable) the system becomes
operational
The following potential causes of false alarms should be considered at the time of the next service visit:
Before the system becomes operational, it should be soak tested in accordance with the recommendations
of BS 5839-1 for a period of: (enter a period of 1 week, the period required by the design
specification, or the period recommended by the signatory to this certificate, whichever period is the
greatest, or delete if not applicable)