Main Document Only.
28/50
Identification: MD-AL-GI-00
Rev. 1.0 07.06.21 - Application: GID
Connext User Manual
Rev. 1.2 07/06/2021
Sensor cable
24-pin terminal block
Black cable
21
Red cable
22
Table 13 - photovoltaic sensor connections
Figure20 – Sensor insertion to measure photovoltaic production from systems not branded Azzurro
The figure shows the direction of the arrow found on the current
sensor. Pay attention to the insertion direction
Note
4.4.2.
Sensor for measuring three-phase photovoltaic
production
If at least one three-phase photovoltaic inverter does not belong to the Azzurro brand and the
photovoltaic production needs to be measured, it is necessary to install an accessory sensor (ZSM-
ACC-TA).
The sensor must be placed directly on the output of the photovoltaic inverter and connected to the
Connext system via pins 21 and 22 of the 24-pin terminal block, as shown below. To ensure correct
calculation of the total power produced, when configuring the system on the APP, specify that the
measurement is made in three-phase.
Sensor cable
24-pin terminal block
Black cable
21
Red cable
22
Table 14 - Photovoltaic sensor connections
Summary of Contents for CONNEXT
Page 1: ...ACCESSORY CONNEXT ...
Page 52: ......