Stop
For wall-side assembly of the scaffold unit, stand-off brackets
can also be used for ballasting (accessory, Order No. 42920).
13. Working on several working platforms simultaneously is not permitted.
14. The permissible load capacity of the scaffold unit with evenly-distributed
load is 2.0 kN/ m² (in accordance with EN 1004 - scaffolding category 3).
15.
There may be no persons, material or tools on the
platform when the scaffold unit is moved. Avoid
collisions. The scaffold unit may only be moved by hand,
in longitudinal or diagonal direction and on a firm,
level surface free of obstacles. The scaffold unit must
not be moved at more than normal walking speed.
16. Moving the scaffold unit with the assistance of
vehicles (e.g. fork lifts) is prohibited. The scaffold unit must not be lifted,
pulled or pushed using a fork lift.
17. The surface on which the scaffold unit is moved must be able to
accommodate its weight.
18.
Bridging the gap between scaffold units and buildings
by means of planks etc. is not permitted.
The scaffold unit must not be used as a stair tower
to reach other constructions.
19.
For use outdoors or in open buildings, the scaffold unit
must be moved into a wind-protected area where wind
strengths exceed 6 (on the Beaufort scale), in the case
of an oncoming storm and when work has been
completed, or it must be protected against tipping
with other suitable measures (e.g. anchoring). At wind
strengths exceeding 6 on the Beaufort scale (12m/s),
it becomes perceptibly difficult to walk forwards.
20. Before using the scaffold unit, its vertical alignment must be checked and
corrected if necessary.
21. The scaffold unit must be checked for correct and complete set-up.