OPERATING & MAINTENANCE MANUAL MODEL : ELB series
YOUYANG AIRPORT LIGHTING EQUIPMENT INC. PAGE 13/34
1)
Prepare the installation drawing for deep base which shall be installed on the
paved runway & taxiway.
2) Mark the installation point of deep base.
3) Cut the area where the deep base shall be installed. (Refer to Figure 3.2)
4) Cut the surface of the asphalt pavement to make the cable conduit through the
cable way.
5) The lower part of cutting comes to the size of min. 152mm extra spacing as the
bottom and of min. 305mm extra spacing as the side.
6) Place the deep base in position.
7) Fix the deep base in line with both directions of runway as shown in the below
figure.
BEAM DIRECTION OF DEEP BASE
8) Connect earth wire and earth rods.
9) Burry the deep base and fill epoxy resin or concrete in a space of the mounted
deep base.
10) Clean and dry thoroughly the deep base.