4.2 Install the suspension bolts 

z

Use a hole-in-anchor for existing ceilings, and a 
sunken insert, sunken anchor or other part to be 
procured in the field to reinforce the ceiling to 
bearing the weight of the unit for new ceiling. 
(Refer to Fig. 3) 

z

Note

˖

 

If the internal insulation material is PE, in 
installation process, please take some preventive 
measure to avoid brazing sparkle contacting the 
insulation material, which may result in fire.   

Fig. 3 Suspension Bolt Installation 

5

INDOOR UNIT INSTALLATION 

5.1 Install the indoor unit temporarily 

z

Attach the hanger bracket to the suspension bolt. 
Be sure to fix it securely by using a nut and washer 
from the upper and lower sides of the hanger 
bracket. (Refer to Fig. 4)

Fig. 4 Indoor Unit Suspension 

5.2 Tighten the nuts and adjust the height of the 
unit to reach the installation site 

5.3 Check if the unit is horizontally   
level

 

z

Make sure that the unit is installed level using a 
spirit level or a plastic tube filled with water. (Refer 
to Fig. 5) 
(One thing to watch out for in particular is if the 
unit is installed so that the slope is not in the 
direction of the drain pipe, which might cause 
leaking.) 

Fig. 5 Check Unit Level 

5.4 Tighten the upper nuts 

z

Be sure the below washer and nut are installed 
within the hanger bracket for fear of bolt rolling 
out, this may result in danger. 

6

REFRIGERANT PIPING WORK 

z

Execute insulation completely on both sides of the 
gas piping and the liquid piping. Otherwise, water 
leakage can result sometimes. 
Please use the insulation materials that can 
withstand temperature of at least 120°C. Reinforce 
the insulation on the refrigerant piping according 
to the installation environment. Otherwise, 
condensate water may form on the surface of the 
insulation. 

Please follow the below items. 

z

Apply ester oil or ether oil to the flare section 
(internal and external surface) when using a flare 
connection. 

z

Only the flare nuts included with the unit can be 
used. Using different flare nuts may cause 
refrigerant leakage. 

z

To prevent dust, moisture or other contaminant 
from infiltrating the piping, either pinch the end or 
cover it with tape. 

z

Do not allow anything other than the designated 
refrigerant to get mixed into the refrigerant circuit, 
such as air, etc. 

z

When brazing the refrigerant piping, perform 
nitrogen replacement first, or perform brazing 
while feeding nitrogen into the refrigerant piping, 
and finally connect the indoor unit using the flare 
connections. 

z

When brazing a pipe while feeding nitrogen inside 
the pipe, make sure to set the nitrogen pressure to 
0.02MPa (0.2kgf/cm2) or less using the pressure 
reducing valve.
(This pressure is just like breeze blowing to your 
cheek.)

NO

TE

NO

TE

NO

TE

CAUTION 

CAUTION 

CAUTION 

Summary of Contents for YDCC06-45

Page 1: ...YORKVRFAir Conditioner 250 12 YDCC IOM English YGF 0911 Installation Manual...

Page 2: ...TY CONSIDERATIONS 2 BEFORE INSTALLATION 2 3 SELECTING INSTALLATION SITE 2 4 BEFORE INSTALLATION 3 5 INDOOR UNIT INSTALLTION 4 6 REFRIGERANT PIPING WORK 4 7 DRAIN PIPING WORK 6 8 INSTALLING THE DUCT 7...

Page 3: ...the doors and windows immediately to ventilate the room thoroughly z Toxic gas may be produced if the refrigerant comes in contact with fire such as a fan heater stove or cooking device z Power off t...

Page 4: ...tdoor unit 3 SELECTING INSTALLATION SITE z If it has the possibility that the temperature and humidity inside the ceiling might exceed 30 C and RH80 please reinforce the insulation on the unit Use gla...

Page 5: ...0 mm2 z Also inspection opening for repairing should be installed in the ceiling right below the unit The size should be no smaller than the unit diameter BhE shown in the Fig 2 YDCC06 45 YDCC018 112...

Page 6: ...installed within the hanger bracket for fear of bolt rolling out this may result in danger 6 REFRIGERANT PIPING WORK z Execute insulation completely on both sides of the gas piping and the liquid pipi...

Page 7: ...nt piping and let the pressure slowly rise to 4 15MPa b The specified pressure should be maintained for 10 minutes and then soapy water or other foaming agent are applied to the connection positions s...

Page 8: ...Central Drain Pipe z For the indoor unit with pump drainage a Be sure the drain raising pipe height is within 700mm b Place the drain raising pipe vertically and make sure it is no further than 300mm...

Page 9: ...rding to the actual pressure drop of the air duct z Indoor unit ESP can be adjusted by changing the connection site of fan wiring in the control board For detail setting method of different indoor ESP...

Page 10: ...system while the other indoor units are controlled by another switch 10 4 Indoor unit field wiring z For detail indoor unit wiring see the Wring Diagram attached to the control box lid when laying the...

Page 11: ...oller can connect to max 4 indoor units Note indoor unit series type of A B C and D is determined by the specific letter in the bar code attached on the unit For example indoor unit YDCC C means C typ...

Page 12: ...721239 YDCC IOM English YGF 0911 NOTHING...

Reviews: