background image

UNIT OPERATION - 090 & 120 MBH

When the external control calls for cooling at terminal Y1:

1. The system controller (SC) is energized. The system con-

troller starts the compressor and enables the condenser
fan(s) by energizing contactor 1M.

Condenser fan motor #1 is energized with the compressor
on the 10 ton model while fan #2 is enabled with compres-
sor operation. Fan motor #2 operation is controlled through
the Ambient Temperature Switch (ATS) which will de-
energize the motor when the ambient temperature falls be-
low 70

°

F.

2. Safety Lockout: The system controller (SC) has a lockout

circuit to prevent compressor short-cycling on a safety con-
trol with automatic reset. If the high or low refrigerant pres-
sure switches (HP or LP) open, the SC will enter lockout
mode.

SC provides a 90 second bypass of the low pressure switch
LP to prevent nuisance lockouts during unit start-up.

A malfunction light (24V, 2 A max. resistive load) can be en-
ergized through SC, by connecting the light between termi-
nals X and B on TB1. Terminal X will energize when SC
locks out.

NOTE: To reset the unit after a lockout:

A. Turn the system switch on the thermostat to the “OFF”

position and back to the “COOL” position.

OR

B. Increase the set point of the room thermostat above the

temperature in the conditioned space and return it to its
original setting.

If the unit continues to be shut down by one of its safety
controls, service should be called to determine the cause of
the problem. Repeated resetting of the lockout circuit may
damage the unit.

035-15406-002-A-0504

12

Unitary Products Group

CRANKCASE HEATER

The crankcase heaters must be energized at least 8 hours before
starting the compressor. To energize the crankcase heaters, the
main disconnect switch must be closed. During this 8 hour peri-
od, the system switch on the room thermostat must be “OFF” to
prevent the compressor from starting.

CAUTION: DO NOT ATTEMPT TO START THE COMPRES-

SOR WITHOUT AT LEAST 8 HOURS OF CRANK-
CASE HEAT OR COMPRESSOR DAMAGE WILL
OCCUR.

Make sure that the bottom of the compressor is warm to the touch
to prove crankcase heater operation.

PRE-START CHECK

Before starting the unit, complete the following check list:

1. Have sufficient clearances been provided?

2. Has all foreign matter been removed from the interior of the

unit (tools, construction or shipping materials, etc.)?

3. Have the condenser fans been rotated manually to check for

free rotation?

4. Are all wiring connections tight?

5. Does the available power supply agree with the nameplate

data on the unit?

6. Is the control circuit transformer set for the proper voltage?

7. Have the fuses, disconnect switch and power wire been sized

properly?

8. Are all compressor hold-down nuts properly secured?

9. Are any refrigerant lines touching each other or any sheet

metal surface? Rubbing due to vibration could cause a refrig-
erant leak.

10. Are there any visible signs of a refrigerant leak, such as oil

residue?

11. Is any electrical wire laying against a hot refrigerant line?

INITIAL START-UP

1. Supply power to the unit through the disconnect switch at

least 8 hours prior to starting the compressor.

2. Move the system switch on the thermostat to the AUTO or

COOL position.

3. Reduce the setting of the room thermostat to energize the

compressor.

4. Check the operation of the evaporator unit per the manufac-

turer's recommendations.

5. With an ammeter, check the compressor amps against the

unit data plate.

6. Check for refrigerant leaks.

7. Check for any abnormal noises and/or vibrations, and make

the necessary adjustments to correct (e.g. fan blade(s)
touching shroud, refrigerant lines hitting on sheet metal, etc.)

8. After the unit has been operating for several minutes, shut off

the main power supply at the disconnect switch and inspect
all factory wiring connections and bolted surfaces for tight-
ness.

OPERATION

START-UP

Summary of Contents for SUNLINE 2000 H4CE120

Page 1: ...eplacement parts on this equipment All forms may be ordered from Standard Register Toll Free Telephone 405 691 1126 Toll Free Fax 405 799 7746 INSPECTION As soon as a unit is received it should be inspected for possible damage during transit If damage is evident the extent of the damage should be noted on the carrier s delivery receipt A separate request for inspection by the carrier s agent shoul...

Page 2: ...nance 13 Cleaning Condenser Surface 13 Lubrication 13 Compressor Replacement 13 TABLES No Description Page 1 Unit Application Data 3 2 Physical Data 4 3 Electrical Data 5 4 Suction Lines 8 5 Liquid Lines 8 6 Refrigerant Line Charge 8 7 Cooling Capacities F 9 8 Cooling Capacities C 9 FIGURES No Description Page 1 Center of Gravity 3 2 Typical Rigging 4 3 Typical Field Wiring 5 4 Unit Dimensions and...

Page 3: ...ot be tied to the building foundation because noise and vibration will telegraph A unit can also be supported by concrete piers These piers should 1 extend below the frost line 2 be located under the unit s four corners and 3 be sized to carry the entire unit weight Refer to Figure 1 and Table 2 for the center of gravity and unit weight CAUTION Care should be taken to protect the unit from tam per...

Page 4: ... general installation procedure Refer to Figure 3 for typical field wiring COMPRESSOR Units are shipped with compressor mountings factory adjusted and ready for operation CAUTION Do Not loosen compressor mounting bolts COMPRESSOR CRANKCASE HEATER The compressor is equipped with a crankcase heater to pre vent refrigerant from mixing with crankcase oil during the OFF cycle The heaters will be energi...

Page 5: ...LECTRICAL DATA TABLE Unit Size MBH Compressor Condenser Fan Motor Total Unit Ampacity Amps Max Fuse Size1 Amps Power Supply RLA LRA Power Supply HP kW Each Qty FLA Each 090 380 415 3 50 17 3 111 220 240 1 50 3 4 56 1 2 9 22 3 30 120 380 415 3 50 19 6 118 220 240 1 50 1 2 37 2 2 1 26 2 35 1 Dual element 2 Based on three 60 C insulated copper conductors in steel conduit TABLE 3 ELECTRICAL DATA ...

Page 6: ...5 8 654 257 64 114 127 5 50 2 105 4 1 8 127 826 AIR OUT AIR IN AIR OUT 70 2 3 4 812 32 57 2 1 4 825 32 1 2 1781 70 1 2 222 8 3 4 136 5 3 8 CONTROL BOX ACCESS GAUGE LINE ACCESS 990 39 28 6 1 1 8 OD SUCTION LINE 15 8 5 8 OD LIQUID LINE 400 15 3 4 22 2 7 8 DIA CONTROL WIRING ENTRY COMPRESSOR AND CONDENSER FAN MOTOR ACCESS 34 9 1 3 8 DIA POWER WIRING ENTRY 171 6 3 4 CONDENSER FAN MOTOR ACCES 22 2 7 8 ...

Page 7: ...t charge The filter drier and is taped to the top of the compressor LINE SIZING When sizing refrigerant lines for a split system air conditioner check the following 1 Suction line pressure drop due to friction 2 Liquid line pressure drop due to friction 3 Suction line velocity for oil return and 4 Liquid line pressure drop due to static head NOTE Never base refrigerant line sizes on the OD of the ...

Page 8: ...2 F 1 1 C change in saturation temperature or approximately 3 psi 21 kPa sizing the lines for the proper return of oil is more important 5 These friction losses do not include any allowances for valves or fittings TABLE 4 SUCTION LINES 1 2 Unit Size MBH Refrigerant Flow Rate1 lbs kg per min Type L Copper Tubing in mm O D Refrigerant Gas Velocity ft m per min Pressure Drop3 Friction2 Vertical Rise ...

Page 9: ...cleaned before being used The liquid line connections can now be brazed while maintain ing a minimum flow of dry nitrogen through the piping as fol lows 1 Remove the cap from the 1 4 6mm access port on the liq uid line service valve 2 Connect a supply of dry nitrogen to this access port NOTE The filter drier and the moisture indicating sight glass should be installed in the liquid line as close to...

Page 10: ...n shipping position See FIG 6 2 Push the service ports through the corner post 3 Tighten the screws to secure the service ports for installa tion EVACUATION AND CHARGING Determine the required weight of refrigerant using Table 2 Physical Data and Table 6 Refrigerant Line Charge Table 2 includes operating charge based on the unit plus 25 feet of re frigerant lines Table 6 includes data required to ...

Page 11: ...035 15406 002 A 0504 Unitary Products Group 11 FIG 5 EXTENDING THE SERVICE PORTS ...

Page 12: ...stat must be OFF to prevent the compressor from starting CAUTION DO NOT ATTEMPT TO START THE COMPRES SOR WITHOUT AT LEAST 8 HOURS OF CRANK CASE HEAT OR COMPRESSOR DAMAGE WILL OCCUR Make sure that the bottom of the compressor is warm to the touch to prove crankcase heater operation PRE START CHECK Before starting the unit complete the following check list 1 Have sufficient clearances been provided ...

Page 13: ...control panel there are no capillary lines to be damaged 035 15406 002 A 0504 Unitary Products Group 13 MAINTENANCE CLEANING CONDENSER SURFACE Dirt should not be allowed to accumulate on the condenser coils or other parts in the condenser air circuit Clean as often as nec essary with a brush vacuum cleaner attachment or other suit able means SECURE OWNER S APPROVAL When the system is functioning p...

Page 14: ...14 Unitary Products Group 035 15406 002 A 0504 ...

Page 15: ...Unitary Products Group 15 035 15406 002 A 0504 ...

Page 16: ...ducts Group 5005 York Drive Norman Oklahoma 73069 Subject to change without notice Printed in U S A Copyright 2004 by Unitary Products Group All Rights Reserved 035 15406 002 A 0504 Supersedes 035 15406 001 B 0404 ...

Reviews: