background image

EXTENDING THE SERVICE PORTS

(see Fig. 6)

1. Loosen the screws that secure the service ports in shipping

position.

2. Push the service ports through the corner post.

3. Tighten the screws to secure the service ports for installa-

tion.

INSTALLATION

Since the condensing units are shipped with a holding charge
of refrigerant-22, they can be checked for a refrigerant leak by
depressing the stem on either of the service ports that extend
through the cabinet.  As soon as some internal pressure is
relieved release the stem.  DO NOT release the entire holding
charge.

If the unit has already lost its holding charge, it should be leak
tested and the necessary repairs should be made. If the unit
has maintained its holding charge, you can assume that it has
no leaks and proceed with the installation.
CAUTION: Dry nitrogen should always be supplied through a

connection while it is being brazed or unbrazed
because the temperature required to make or
break a brazed joint is sufficiently high to cause
oxidation of the copper unless an inert atmosphere
is provided. The flow of nitrogen should be contin-
ued until the joint has cooled.
When making a braze connection, wrap a wet rag
around all tubing inside the unit to help prevent
damage to other components.

WARNING: The dry nitrogen should always be supplied

through a pressure regulating valve.

Before installing the liquid line between the condensing unit and
the evaporator coil, prepare as follows:

1. Burnish the external surfaces of the liquid connection on

the condensing unit and the end of the field-supplied piping
for the liquid line.
NOTE: Clean surfaces are essential for a well-brazed con-

nection.

2. Carefully clean the internal surfaces of the above. Any

particles left on these surfaces may lead to a future system
malfunction.
NOTE: Use only copper tubing that has been especially

cleaned and dehydrated for refrigerant use. If the
tubing has been open for an extended period of
time, it should be cleaned before being used.

The liquid line connections can now be brazed while maintaining
a minimum flow of dry nitrogen through the piping as follows:

1. Remove the cap from the 1/4" access port on the liquid line service

valve.

2. Connect a supply of dry nitrogen to this access port.

NOTE: The filter-drier should be installed in the liquid line

as close to the evaporator coil as possible.
Do not allow the filter-drier to be exposed to the
atmosphere for an extended period of time. Once
it absorbs moisture from the atmosphere, it loses
its effectiveness.

The matched air handlers are shipped with a small R-22 charge
and the should be checked for leaks before installation.

1. Drill a small hole through the sealing cap or disc in both  the

liquid and suction connection.  If there is a pressure release,
the evaporator has no leaks and you can proceed with
installation.  If the charge has been lost, the coils should be
leak tested and the necessary repairs made

2. Move the dry nitrogen supply from the access port on the

liquid line service valve of the condensing unit to the hole
through the suction disc on the evaporator coil.

3. Unbraze the coil’s liquid line disc while maintaining a flow

of dry nitrogen across the connection and through the hole
in the liquid line disc.
NOTE: If the liquid line has a solenoid valve, the valve

should be opened manually to permit the nitrogen
to flow freely.

4. After the disc has been removed, burnish the external

surfaces and clean the internal surfaces as outlined above.

5. Move the dry nitrogen supply back to the access port on

the liquid line service valve.

6. Braze the liquid line to the liquid connection on the evapo-

rator coil while maintaining a minimum flow of dry nitrogen
through the liquid line, the evaporator coil and the hole in
the suction disc.

7. Unbraze the disc on the suction connection of the evapo-

rator coil while maintaining the flow of dry nitrogen.

8. After the disc has been removed, burnish the external

surfaces and clean the internal surfaces as outlined above.

The suction piping can now be brazed to the suction connection
on the evaporator coil while maintaining a minimum flow of dry
nitrogen.

Before brazing the suction line to the condensing unit;

1. Move the dry nitrogen supply to the access port on the

suction service valve of the condensing unit.

2. Burnish the external surfaces and clean the internal sur-

faces of both the suction connection and the suction piping.

The suction line can now be brazed to the suction connection
on the condensing unit while maintaining the flow of dry nitro-
gen.

After the liquid and suction lines have been installed, the
system should be evacuated and charged.

EVACUATION AND CHARGING

With the liquid and suction line service valves closed, connect
a vacuum pump through a charging manifold to the access
ports on both the liquid and suction line service valves.

NOTE: The vacuum pump connection should be short and

no smaller than 3/8" O.D.

The refrigerant lines and the evaporator coil can now be evacu-
ated to 500 Microns without disturbing the charge in the con-
denser coil or the compressor.

After proper evacuation and dehydration, charge refrigerant
through the access port on the liquid line service valve allowing
the vacuum to draw in as much refrigerant as possible.

CAUTION: Do not charge liquid refrigerant through the com-

pressor suction connection.

CAUTION: Do not attempt to start the compressor without at

least 8 hours of crankcase heat or compressor
damage will occur.

To continue charging refrigerant, open the liquid and the suction
line service valves fully.  Turn the stem of the liquid service valve
clockwise 

1

/

4

 turn to open its access port for reading pressure.

Start the compressor (after 8 hours of crankcase heat), turn the
stem of the suction line service valve clockwise 

1

/

4

 turn to open

its service port and continue to charge refrigerant gas through
this suction access port until you meet the conditions shown
on the charging curve, Fig. 7.

Open the liquid and vapor line service valves fully to close their
access ports after the system has been charged.

550.23-N6Y

Unitary Products Group

9

Summary of Contents for H3CE180

Page 1: ...f the evaporator blower units refer to instruction Form 550 23 N4Y All accessories come with a separate Installation Manual Refer to Parts Manual for complete listing of replacement parts on this equi...

Page 2: ...Secure Owner s Approval 12 Maintenance 12 Cleaning Condenser Surface 13 Lubrication 12 Compressor Replacement 12 TABLES No Description Page 1 Unit Application Data 3 2 Physical Data 4 3 Electrical Dat...

Page 3: ...4 Footers under the slab that extend below the frost line are recom mended Anystrainontherefrigerantlinesmaycausearefrigerant leak Theslabshouldnotbetiedtothebuildingfoundationbecause noise and vibra...

Page 4: ...r general installation procedure Refer to Figure 3 for typical field wiring COMPRESSOR CRANKCASE HEATER The compressor is equipped with a crankcase heater to prevent refrigerant from mixing with crank...

Page 5: ...R S H 3 C E 1 8 0 K 1 E U 1 8 0 H 3 C E 2 4 0 L 3 E U 2 4 0 3 P H A S E L I N E V O L T A G E P O W E R S U P P L Y 3 P H A S E L I N E V O L T A G E P O W E R S U P P L Y 3 P H A S E L I N E V O L T...

Page 6: ...A C C E S S E X T E R N A L P R E S S U R E G A U G E F I T T I N G S C O N T R O L B O X A C C E S S 9 1 3 2 7 6 7 8 7 1 3 2 3 9 7 8 1 3 1 4 3 0 3 4 2 4 1 2 1 2 1 8 C D F E F E F A B All dimensions a...

Page 7: ...on line must be sized for both pressure drop and for oil return For certain piping arrangements different suction line sizes may have to be used The velocity of the suction gas must always be great en...

Page 8: ...oor system performance but could also damage the expansion valve TABLE 5 LIQUID LINES Liquid Line2 Inches O D 5 8 0 113 lb ft 7 8 0 237 lb ft Suction Line2 Inches O D 1 5 8 0 018 lb ft 2 1 8 0 031 lb...

Page 9: ...rom the access port on the liquid line service valve of the condensing unit to the hole through the suction disc on the evaporator coil 3 Unbraze the coil s liquid line disc while maintaining a flow o...

Page 10: ...f the refrigerant for the total system by adding the required charge for the outdoor unit the indoor unit and the refrigerant lines using information in Tables 2 Physical Data and 6 Refrigerant Line C...

Page 11: ...F Ambient 95 F Ambient 85 F Ambient 75 F Ambient Charging Curve H CE240 200 250 300 350 400 57 62 67 72 77 82 87 92 97 Suction Pressure Discharge Pressure 115 F Ambient 105 F Ambient 95 F Ambient 85...

Page 12: ...rgized locking out cooling operation until the call for cooling has been removed When Y1 is returned to 0 volts the LOR coil is no longer energized closing the LOR 1 contacts and removing the lock out...

Page 13: ...ration to 0 F SAFETY FEATURES 1 The compressor is protected against over current and excessive temperature as described in the Sequence of Operation 2 The compressor is equipped with a crankcase heate...

Reviews: