background image

5121495-UIM-D-0516

4

Johnson Controls Unitary Products

PIPING CONNECTIONS

The outdoor condensing unit must be connected to the indoor evapora-
tor coil using field supplied refrigerant grade (ACR) copper tubing that is
internally clean and dry. Units should be installed only with the tubing
sizes for approved system combinations as specified in tabular data
sheet. The charge given is applicable for total tubing lengths up to 15
feet (4.6 m). See Piping Application Guide (P/N 247077) for installing
tubing of longer lengths and elevation differences.

PRECAUTIONS DURING LINE INSTALLATION

1.

Install the lines with as few bends as possible. Care must be taken
not to damage the couplings or kink the tubing. Use clean hard
drawn copper tubing where no appreciable amount of bending
around obstruction is necessary. If soft copper must be used, care
must be taken to avoid sharp bends which may cause a restriction.

2.

The lines should be installed so that they will not obstruct service
access to the coil, air handling system, or filter.

3.

Care must also be taken to isolate the refrigerant lines to minimize
noise transmission from the equipment to the structure.

4.

The vapor line must be insulated with a minimum of 1/2” foam rub-
ber insulation (Armaflex or equivalent). Liquid lines that will be
exposed to direct sunlight, high temperatures, or excessive humid-
ity must also be insulated.

5.

Tape and suspend the refrigerant lines as shown. DO NOT allow
tube metal-to-metal contact. See Figure 2.

6.

Use PVC piping as a conduit for all underground installations as
shown in Figure 3. Buried lines should be kept as short as possible
to minimize the build up of liquid refrigerant in the vapor line during
long periods of shutdown.

7.

Pack fiberglass insulation and a sealing material such as perma-
gum around refrigerant lines where they penetrate a wall to reduce
vibration and to retain some flexibility.

8.

For systems with total line length exceeding 75 feet (22.86 m), see
Piping Application Guide (P/N 247077) for vapor and liquid line
sizing, calibration of liquid line pressure loss or gain, determination
of vapor line velocity, elevation limitations, TXV connections, sys-
tem charging, traps, etc.

PRECAUTIONS DURING BRAZING OF LINES

All outdoor unit and evaporator coil connections are copper-to-copper

and should be brazed with a phosphorous-copper alloy material such
as Silfos-5 or equivalent. DO NOT use soft solder. The outdoor units
have reusable service valves on both the liquid and vapor connections.
The total system refrigerant charge is retained within the outdoor unit
during shipping and installation. The reusable service valves are pro-
vided to evacuate and charge per this instruction.

Serious service problems can be avoided by taking adequate precau-
tions to assure an internally clean and dry system.

PRECAUTIONS DURING BRAZING SERVICE VALVE

Precautions should be taken to prevent heat damage to service valve
by wrapping a wet rag around it as shown in Figure 4. Also, protect all
painted surfaces, insulation, and plastic base during brazing. After braz-
ing, cool joint with wet rag.

Valve can be opened by removing the service valve cap and fully insert-
ing a hex wrench into the stem and backing out counter-clockwise until
valve stem just touches the chamfered retaining wall.

Connect the refrigerant lines using the following procedure:

1.

Remove the cap and Schrader core from both the liquid and vapor
service valve service ports at the outdoor unit. Connect low pres-
sure nitrogen to the liquid line service port.

2.

Braze the liquid line to the liquid valve at the outdoor unit. Be sure
to wrap the valve body with a wet rag. Allow the nitrogen to con-
tinue flowing.

3.

Carefully remove the plugs from the evaporator liquid and vapor
connections at the indoor coil.

NOTICE

Using a larger than specified line size could result in oil return prob-
lems. Using too small a line will result in loss of capacity and other
problems caused by insufficient refrigerant flow. Slope  horizontal
vapor lines at least 1" (2.5 cm) every 20 feet (6.1 m) toward the out-
door unit to facilitate proper oil return. If more than the 75 foot line
length is necessary, facilitate proper refrigerant velocity with
adjusted line diameter in accordance with the Piping Application
Guide (P/N 247077). 

 CAUTION

This system uses R-410A refrigerant which operates at higher pres-
sures than R-22. No other refrigerant may be used in this system.
Gauge sets, hoses, refrigerant containers, and recovery system
must be designed to handle R-410A. If you are unsure, consult the
equipment manufacturer.

 WARNING

Never install a suction-line filter drier in the liquid line of an R-410A
system. Failure to follow this warning can cause a fire, injury or
death.

 FIGURE 2:  

Installation of Vapor Line

!

!

$

+$1*(5

/,48,'
/,1(

,1&255(&7

&255(&7

,168/$7('9$325/,1(

7$3(

 FIGURE 3:  

Underground Installation

 CAUTION

Dry nitrogen should always be supplied through the tubing while it is
being brazed, because the temperature required is high enough to
cause oxidation of the copper unless an inert atmosphere is provided.
The flow of dry nitrogen should continue until the joint has cooled.

Always use a pressure regulator and safety valve to insure that only

low pressure dry nitrogen is introduced into the tubing. Only a small
flow is necessary to displace air and prevent oxidation.

 WARNING

This is not a backseating valve. The service access port has a valve
core. Opening or closing valve does not close service access port.
If the valve stem is backed out past the chamfered retaining wall, the
O-ring can be damaged causing leakage or system pressure could
force the valve stem out of the valve body possibly causing personal
injury.

TO INDOOR COIL

TO OUTDOOR UNIT

LIQUID LINE

CAP

PVC
CONDUIT

INSULATED

VAPOR LINE

A0152-001

!

!

Summary of Contents for 14 SEER-TH4 SERIES

Page 1: ...ng indoor coils can be used with a thermostatic expansion valve TXV Refer to the Tabular Data Sheet or to the Technical Guide for the proper selection SECTION II SAFETY This is a safety alert symbol W...

Page 2: ...e preferred method is to weigh in the charge For charging or checking the system charge at 55 F or below refer to the Optional Cold Weather Charging procedures near the end of SECTION VI SYSTEM CHARGE...

Page 3: ...ess and serviceability as well as the possible sound and vibration transmission into the structure These applications are best served by a properly engineered solution UNIT PLACEMENT 1 Provide a base...

Page 4: ...internally clean and dry system PRECAUTIONS DURING BRAZING SERVICE VALVE Precautions should be taken to prevent heat damage to service valve by wrapping a wet rag around it as shown in Figure 4 Also...

Page 5: ...ischarged loosen and remove the Schrader core 3 Place a backup wrench on distributor loosen and remove brass distributor nut Retain brass nut for use on liquid line Keep teflon washer in place and dis...

Page 6: ...gerant charge added accordingly MEASURE INDOOR AIR FLOW To determine rated air flow for a specific match consult the technical lit erature at www upgnet com When attempting to match this air flow sele...

Page 7: ...control box can swing open by removing the screw from the center of each side of the control box and allowing the control box to lower an inch or so into a pivotal position The control box can then s...

Page 8: ...disconnect switch to the unit 4 Route wires from disconnect through power wiring exit provided and into the unit control box as shown in Figures 9 10 5 Install the proper size time delay fuses or cir...

Page 9: ...www upgnet com in the Product Catalog Section INDOOR CUBIC FEET PER MINUTE CFM SELEC TION BOARD SETTINGS Typical Refer to the indoor unit Installation Manual instructions for the air han dler or furna...

Page 10: ...owing table summarizes the behavior of the control when the two TEST pins are connected More detailed descriptions of the various functions are included in other sec tions of this document TABLE 3 TES...

Page 11: ...arrangement of the refrigeration circuit within the coil The control may initiate a defrost cycle even when the coil is not completely cov ered with frost This is normal operation The control regulat...

Page 12: ...cur regardless of the liq uid line coil temperature reading The coil does not have to be cold for the unit to be forced into defrost Once the defrost cycle begins the con trol shall follow the normal...

Page 13: ...h code The control will reset the soft lockout condition when any of the follow ing occur after removal of the fault condition 1 Power is cycled to the R or Y inputs of the control This will cause the...

Page 14: ...AL SHOCK OPEN REMOTE DISCONNECT SO ELECTRICAL SUPPLY TO HEAT PUMP IS SHUT OFF COMPONENTS SHOWN IN DASH LINES ARE OPTIONAL DUAL CAPACITOR SHOWN SEPARATE CAPACITORS MAY BE USED ON ACTUAL UNIT WIRING MUS...

Page 15: ...5121495 UIM D 0516 Johnson Controls Unitary Products 15 NOTES...

Page 16: ...plicable Electrical Line Voltage Outdoor Unit Model Outdoor Unit Serial Filter Thermostat Accessories Filter Location s Connections Per Installation Instructions and Local Codes Gas piping is connecte...

Page 17: ...mp Cut Out Balance Point Defrost Curve Y2 Lock FFUEL Switch Point Hot Heat Pump Fill in the information ie ON OFF or the appropriate Value for the fields that apply to the defrost control board instal...

Page 18: ...des 5121495 UIM C 0316 York International Corp 5005 York Drive Norman OK 73069 Explain operation of system to equipment owner Explain the importance of regular filter replacement and equipment mainten...

Reviews: