background image

Y I N G L I S O L A R .CO M

©

 Yingli Energy Development Company Limited           

GB Modules Installation and User Manual  Page 5 

Landscape Orientation

Portrait Orientation

snow load), depending on the module type (please refer to the data sheet for this 

information).

Installation structures and other mechanical parts must be designed and approved 

to  withstand  the  design  wind  and  snow  loads  applicable  for  a  particular  site. 

Yingli Solar PV modules must not be subjected to forces from the substructure, 

including forces caused by thermal expansion. 

The installation method must not result in the direct contact of dissimilar metals 

with the aluminum frame of the PV module that will result in galvanic corrosion. An 

addendum to UL Standard 1703 “Flat Plate Photovoltaic Modules and Panels” 

recommends  metal  combinations  not  exceed  an  electrochemical  potential 

difference of 0.5 Volts. Yingli Solar PV modules can be mounted in landscape 

or  portrait  orientation,  as  illustrated  in  Figure  10,  provided  that  the  installation 

method follows one of the acceptable methods listed below. 

Figure 10: Landscape and portrait installation

In  order  to  maintain  the  fire  class  rating,  the  distance  between  the  PV  module 

front surface (glass) and the roof surface shall be at least 10 cm. This spacing 

also allows air flow to cool the PV module. Install PV modules with a minimum 

spacing of 1 cm between neighboring frames to allow for thermal expansion.

Installation Methods

The following installation methods are available:

Bolts or Clamps

Refer  to  figure  12  and  13.  Do  not  modify  the  existing  installation  holes  or  drill 

new holes. Do not apply excessive pressure on the frame such that the frame 

deforms.

  Bolts: Modules must be mounted using the installation holes located on the rear 

side of the long frame parts using M8 stainless steel bolts, nuts, and washers. 

The torque of screw tightening should between 14N·m to 20N·m.

 
 
 
 
 
 
 
 

Figure 11: Detail of a bolt installation attachment

Figure 12 : Installation rails

The large size modules are mounted with four outer holes, with max mechanical 

loads of 5400 Pa snow (front) and 2400 Pa wind (back).

  Top-down  Clamps:  Third-party  clamps  that  have  been  designed  for  PV 

installation  structures  are  an  approved  installation  attachment  method  for 

Yingli Solar PV modules. Modules must be fastened using clamps applied to 

the top side of the long frame parts. A clamp holds two modules except for the 

clamps at the beginning and end of a module row. The module clamps should 

not contact with the front glass and deform the frame. and avoiding shadowing 

effects from the module clamps. The module frame is not to be modified under 

any circumstances. The applied torque value should be big enough to fix the 

modules  steadily,  the  torque  of  screw  tightening  should  between  16  N·m  to 

24 N·m.  

 
 
 
 
 
 
 
 

Figure 13: Detail of a top-down clamp installation attachment

M A I N T E N A N C E

General

Yingli  Solar  recommends  that  PV  systems  be  periodically  inspected  by  the 

installer, or other qualified person. 

The purpose of the PV system inspection is to ensure that all system components 

are  functioning  properly.  At  a  minimum,  this  inspection  should  confirm  the 

following:

  All cables and connector attachments are undamaged and properly secured

 No sharp objects are in contact with the PV module surfaces

  PV modules are not shaded by unwanted obstacles and/or foreign material

  Installation and grounding components are tightly secured with no corrosion

Defects should be addressed immediately. 

Cleaning

Over  time,  dirt  and  dust  can  accumulate  on  the  glass  surface  of  the  module, 

reducing  its  power  output.  Yingli  Solar  recommends  periodic  cleaning  of  PV 

modules  to  ensure  maximum  power  output,  especially  in  regions  with  low 

precipitation. 

Screw

Backing Nut

Nut Washer

PV Laminate

Mounting Rail

Aluminum Frame

L

L

Inner Four-hole Installation

Long Frame Side Clamp Installation -1
       (Clamp Length≥40mm)

L

L

L

Outer Four-hole Installation

Long Frame Side Clamp Installation -2
       (Clamp Length≥40mm)

Short Frame Side Clamp Installation -2

       (Clamp Length≥40mm)

Inner Four-hole installation

Outer Four-hole installation

Summary of Contents for YLM 144CELL 182PERC

Page 1: ...ication requirements has been verified by an independent certification laboratory This Installation and User Manual is available in different languages In cases of discrepancy between versions the Eng...

Page 2: ...ng so may degrade performance or cause irreparable damage and will void any applicable warranties If it is necessary to store PV modules prior to installation the PV modules should remain inside the p...

Page 3: ...suitable cross sectional areas that are approved for use at the maximum short circuit current of the PV module Yingli Solar recommends installers use only sunlight resistant cables qualified for dire...

Page 4: ...ult in galvanic corrosion An addendum to UL Standard 1703 Flat Plate Photovoltaic Modules and Panels recommends metal combinations not exceed an electrochemical potential difference of 0 5 Volts The f...

Page 5: ...hment Figure 12 Installation rails The large size modules are mounted with four outer holes with max mechanical loads of 5400 Pa snow front and 2400 Pa wind back Top down Clamps Third party clamps tha...

Page 6: ...e materials that could scratch or damage the glass surface Failure to comply with these requirements may adversely affect the PV module performance Yingli Solar PV modules are designed to withstand hi...

Page 7: ...l characteristics are within 10 percent of the indicated values of Isc Voc and Pmax under Standard Test Conditions irradiance of 1000 W m2 AM 1 5 spectrum and a cell temperature of 25 Refer to module...

Page 8: ...f 14 20 N m The tightening steps as follows use torque wrench to tighten nut to target torque nut loosen 90 180 degrees finally tighten the nut to the target torque and reduce the torque attenuation 2...

Page 9: ...ashers of minimum 1 4 mm thickness with an minimum outer diameter of 15 57 mm Modules can be attached using the mounting holes the number of mounting holes used for a single long side frame 2 includin...

Page 10: ...when it is pressed down L represents the length of the long side of the module the described distances are from the module edge to the middle of the clamp The long side frames of the module are fixed...

Page 11: ...ropes are required to secure the modules to the forklift with a tensile strength greater than 2000 kgf 2 Pass the forearm of the anti tilting bracket through the pallet insert the two bolts into the...

Reviews: