18 | RMB/ENERGIE GmbH
assembly
Operation manual CHP 5.0 - 30.0 | Status 01.2020
5.3 Assembly steps
Brief overview:
5.3.3 Positioning the generation unit
5.3.4 Screwing the control cabinet in position
5.3.5 Screwing the expansion tank connection block in
5.3.6 Connecting the generation unit
5.3.7 Connecting the temperature sensors
5.3.9 Connecting the control cabinet
5.3.10 Checking the connections
5.3.1 Preparing for assembly
A
Familiarise yourself with the assembly situation and
the documentation.
B
System
B
System components
B
Safety devices
B
Accessories
B
Installation location
B
Operation manual and supporting documents
A
Gather together the required tools and materials.
A
Keep the assembly area clear of objects than may
get in the way or be damaged.
A
Check that all of the installation location
requirements have been fulfilled.
D
“5.2 Installation location requirements”
A
Ensure that the supply voltage has been and
remains disconnected. Only connect the supply
voltage when instructed in the respective assembly
step.
If accessories (e.g. flue gas silencer, exhaust air kit)
are required for the assembly process:
A
Ensure that the accessory is correctly assembled
and ready for connection.
A
Ensure that the lines from the accessories have
been laid correctly and are accessible.
Manuals for accessories.
5.3.2 Unpacking the system
D
ATTENTION!
Risk of damage caused by improper handling!
The system may be damaged during unpacking or
transportation.
A
Do not cut through the protective packaging.
A
Keep objects that might damage the system away
from it (e.g. tools).
A
Remove the packaging material from the system.
A
Remove the parts included in the scope of delivery
from on top of the generation unit.
A
Check the system and all the parts it contains for
damage.
A
Check the scope of delivery according to the
delivery note for completeness.
If parts are missing or damaged:
A
Contact the manufacturer.
A
Remove the packaging material from the installation
location.
D