Alyza IQ NH4
Commissioning
33
ba76202d02
05/2020
Positioning the
stand mount
Make sure that both triangular stabilizing sheets (5) are on the in-
side.
figure 3-4 Mounting the retaining hooks
1
Retaining hook
6
Mount the four retaining hooks (1) on the supporting pipes. For each
hook, use two hexagon head screws, large plain washers, spring wash-
ers and locknuts.
On each side there are three pairs of holes for the upper and lower
retaining hooks. Thus the Alyza IQ can be mounted optimally at
working level. Use the same relative positions for each of the upper
and lower hooks.
1
7
Place the stand mount at the intended operating location.