Installation of the Alyza IQ includes the following main steps:
3.3.4 Installing the housing
The housing of the Alyza IQ can be installed in the following ways:
On the SM stand mount (see section 3.3.5 Installation on the SM stand
mount,
On a rail (see section 3.3.6 Installation on a rail,
On a wall (see section 3.3.7 Installation on a wall,
40).
1
Installing the housing (see section 3.3.4 Installing the housing,
2
Removing the transport protection of the measuring unit (see
section 3.3.8 Removing the transport protection of the measuring unit,
42).
3
4
5
Installing the bug screen and condensate drain adapter (see
section 3.3.11 Installing the bug screen and condensate drain adapter,
45).
6
With the relevant accessories:
Mounting the terminal holder (TM) (see section 3.3.12 Mounting the ter-
minal holder (TM),
7
Mounting the collection funnel (see section 3.3.14 Mounting the collec-
tion funnel,
8
With the relevant accessories:
Installing the FM/PC filter module and M 1.5 basin holder for filtration
(see section 3.3.16 Installing the FM/PC filter module and M 1.5 basin
holder for filtration,
9
With the relevant accessories:
Connecting the power cable and heat tracing lines (see section 3.3.13
Connecting the power cable and heat tracing lines,
50).
10
Setting up a connection with the IQ S
system (see
section 3.3.18 Setting up a connection with the IQ S
69).