9.1
Installation Checklist
Site Name
Address
Detector Serial Number(s) and Date of
Manufacture
Name of Installer
Signature
Date
Perform the following checks listed below to ensure that all the necessary items are completed before handing
over to a commissioning engineer.
Installation Checks
Yes
No
Were the detector and the mounting bracket intact in the box?
Is the detector securely locked onto its mounting bracket?
Is the sampling air pipe firmly connected to the air inlet port? Ensure the
pipe is NOT glued.
Have the power wires been connected to the correct terminals on the
detector?
If required, has the end of line resistor been connected?
Have the alarm signaling wires been terminated to the correct terminals
on the detector?
Are the VESDAnet terminals looped back on a standalone VESDAnet
enabled detector? Refer to Section 6.1.1 on page 20 for further
information.
Is the exhaust pipe firmly fitted to the exhaust port? Ensure the pipe is
NOT glued.
Have both the plastic and stainless steel front covers been replaced
correctly?
Has AutoLearn Smoke been performed?
Please state the AutoLearn Smoke period____________
Is the air sampling pipework installed and checked as per the site plans?