Depending on the demand the connection can be done in two ways:
Variant 1
: Buffered supply voltage via an UPS
Procedure:
1.
Locate
terminal strip (-X1) (Figure 14).
2.
Open
corresponding cable ducts.
3.
Connect
PE, N and L conductor of the
UPS
to the terminal strip (-X1):
o
Protective conductor PE to (-X1.7)
o
Neutral conductor N to (-X1.3) or (-X1.4)
o
Phase L to (-X1.1) or (-X1.2)
4.
Connect
PE, N and L conductor of the
unbuffered supply voltage
to the
terminal strip (-X1):
o
Protective conductor PE to (-X1.7)
o
Neutral conductor N to (-X1.6)
o
Phase L to (-X1.5)
5.
Close
cable ducts.
Variant 2
: Unbuffered supply voltage
Procedure:
1.
Locate
terminal strip (-X1) (Figure 14).
2.
Open
corresponding cable ducts.
3.
Bridge
the terminals as follows:
o
(-X1.1) or (-X1.2) to (-X1.5)
o
(-X1.3) or (-X1.4) to (-X1.6)
4.
Connect
PE, N and L conductor to the terminal strip (-X1):
o
Protective conductor PE to (-X1.7)
o
Neutral conductor N to (-X1.6)
o
Phase L to (-X1.5)
5.
Close
cable ducts.