8 Decommissioning
Procedure:
1.
Stop
the product (Section 5.6).
2.
Switch off
the AC/DC voltage externally and
secure
it from being switched on
again.
3.
Ensure
that the product is de-energized.
4.
Disconnect
the AC/DC cables.
5.
Ensure
that the AC/DC cables are permanently de-energized.
6.
Ensure
that no residual voltage is present within the DC link by means of
suitable testing equipment (Figure 5).
7.
Ensure
that no residual voltage is present within the harmonic filter by means
of suitable testing equipment (Figure 5).
8.
Switch off
voltage measurement and supply voltage (Section 8.1) and
disconnect
the lines.
9.
Ensure
that the lines for supply voltage are permanently de-energized.
10.
Disconnect
Ethernet cable and any other connected cables and lines.
8.1
Disconnecting Voltage Measurement and Supply Voltage
By switching the motor protecting switch (-F31) in position
0
, the voltage measurement
is disconnected from the grid (Figure 5).
The supply voltage is externally connected from outside and can be disconnected by
means of external fusing.