Additional Conditions
The functions described above for terminal 6 are dependent upon the conditions listed in Table 4-3 in conjunction
with the states of the discrete inputs. The desired function must also be enabled when configuring the control unit.
Condition
A
Synchronization
Generator circuit breaker
Generator frequency and voltage must meet the following conditions:
-
50 % < V < 125 % of the rated voltage V
N
-
80 % < f < 110 % of the rated frequency f
N
The synchronization will be aborted after monitoring time expires
B
Dead bus start
Generator circuit breaker
-
Parameter "Dead bus start GCB" is configured "ON"
-
Synchronization reference voltage must be less than 5% of the rated voltage
-
Generator voltage and frequency must be within the configured limits of the dead
bus start
C1
Automatic no-load control
-
Parameter "Automatic no-load control" is configured "ON"
The frequency controller applies to the following conditions:
-
Generator voltage > 50 % of the rated voltage V
N
- The voltage controller applies to the following conditions:
Generator frequency > 90 % of the rated frequency f
N
C
No-load operation
The frequency controller applies to the following conditions:
-
Generator voltage > 50 % of the rated voltage V
N
- The voltage controller applies to the following conditions:
Generator frequency > 90 % of the rated frequency f
N
D
Isolated operation
The frequency controller applies to the following conditions:
-
Parameter "Frequency controller in isolated operation" is configured "ON"
-
Generator voltage > 50 % of rated voltage V
N
The voltage controller applies to the following conditions:
-
Parameter "Voltage controller in isolated operation" is configured "ON".
-
Generator frequency > 90 % of rated frequency f
N
Table 5-3: Operating conditions - terms