Manual 02029
Load Sharing Module (Analog Output)
Woodward
7
Installation Check
Before initial operation of the Load Sharing Module, make the following visual
checks.
1.
Check that the control is securely mounted.
2.
Check that all electrical connections are correctly made and that all terminal
screws are tight.
3.
Check that shielded wire is installed on the wires indicated in the plant
wiring diagram, and that all shields are grounded on one end only.