background image

7

2095-0

60706-230

MAINTENANCE

GENERAL

The main components of the generator are:  field 

frame, field coils, armature, brushes. brush holder 

assembly, brackets, armature, and generator cooling 

fan.

BRUSHES

Under ordinary circumstances brushes will operate 

for thousands of hours without requiring replace-

ment.  They should be inspected after the first 

000 hours of operation, and after every 500 hours 

of operation thereafter.  Remove brushes one at 

a time and check for length.  Be sure that each 

moves freely in the brush holder.  Brushes should be 

replaced when worn down to 3/8”.  Always replace 

brushes in complete sets, never singularly.  When 

replacing brushes be careful to reconnect the lead 

wire properly.  Poor contact or “skipping” between 

brush and slip ring can be caused by oil and grit, 

flint, or other hard contaminant substances on the 

brushes, or by the brush not being properly shaped 

to fit the slip rings.  

Remedy these defects by cleaning the rings and 

brushes and then fitting the brushes to the slip ring 

curvature.  Place #00 sandpaper under the brushes 

with the abrasive side to the brushes, and work it 

back and forth until the brushes are the same shape 

as the slip rings.

SLIP RINGS

The continuous copper rings located at the end of 

armature are the power collector rings or ‘slip rings’.  

For proper generator output, the surface of these slip 

rings must have a highly polished finish.  Under sus

-

tained use, it is advisable to check and occasionally 

polish ring surfaces with a crocus cloth to maintain 

the finish under normal conditions.  This should not 

be required more than once each thousand hours of 

operation.

ELECTRICAL TESTING

TESTING COILS FOR OPENS AND GROUNDS

 

1.  Disconnect field leads from rectifier.

2.  Set multi-meter to read resistance, and connect 

the meter leads to the field leads.  If field is open, 

meter will read infinite resistance (very high ohms), 

repair or replace field if it is open.  Typical resistance 

for these fields varies from 12.8 to 14.1 ohms.

3.  Leaving one meter lead connected to the field, 

connect the other meter lead to the field shell.  If 

meter indicates continuity (any reading - should be 

infinite resistance), the field is grounded and should 

be repaired or replaced.  To determine which of the 

fields is grounded, cut the connector between the 

two coils and retest to determine which coil has the 

low resistance path.

Summary of Contents for 2FS Series

Page 1: ... 12095 10 60706 230 INSTALLATION AND OPERATORS MANUAL 2FS Generators 2000 Watt Belt Drive 225 S CORDOVA AVE LE CENTER MN 56057 507 357 6821 SERVICE DEPARTMENT 507 357 6831 www wincogen com ...

Page 2: ...S 4 PREPARING THE UNIT 5 Unit Installation 5 MAINTENANCE 6 ELECTRICAL TESTING 7 TROUBLESHOOTING 8 ILLUSTRATED PARTS LIST 9 WIRING DIAGRAM 10 MAINTENANCE LOG 11 WARRANTY INFORMATION 12 PROPER USE AND INSTALLATION You must be sure your new generator set is Properly serviced before starting Operated in a well ventilated area Properly exhausted and gases safely dispersed Operated only for its designed...

Page 3: ...nly three pronged grounded receptacles and extension cords e Be sure the unit is properly grounded 2 FIRE HAZARD Gasoline and other fuels pres ent a hazard of possible explosion and or fire a Do not refuel when the engine is running or hot b Keep fuel containers out of reach of children c Do not smoke or use open flame near the gen erator set or fuel tank d Keep a fire extinguisher nearby and know...

Page 4: ...P type The chart below shows the approximate current required to start and run various types and sizes of 120 volt 60 cycle electric motors under average load conditions HP AMPS RUNNING STARTING AMPS SP CAP RI 1 6 3 2 16 to 22 6 to 13 5 to 8 1 4 4 5 22 to 32 9 to 18 7 to 12 1 3 5 2 26 to 35 10 to 21 8 to 17 1 2 7 2 not made 14 to 29 11 to 18 1 13 0 not made 26 to 52 20 to 33 The figures given abov...

Page 5: ...rime mover generator pulley ratio to drive the generator at the correct operating speed bear in mind that the power rating of most prime mov ers usually an engine varies with the speed It produces more power at higher speeds less when slowed The prime mover must be run fast enough to reach the desired horsepower for good generator operation The drive belt system must be of adequate size and must b...

Page 6: ...TION Generally these two bearing generators are used on portable equipment For best service consider the following 1 All electrical equipment should be protected from excessive moisture Failure to do so will result in deterioration of the insulation and short circuits and grounds 2 The generator should be installed in a sheltered area If the unit must be left in the open it should always be protec...

Page 7: ...e side to the brushes and work it back and forth until the brushes are the same shape as the slip rings SLIP RINGS The continuous copper rings located at the end of armature are the power collector rings or slip rings For proper generator output the surface of these slip rings must have a highly polished finish Under sus tained use it is advisable to check and occasionally polish ring surfaces wit...

Page 8: ...inding is open This may be caused by a re pairable defect in the connection at the slip ring however generally an open armature will have to be replaced TESTING RECTIFIERS The field excitation is supplied through full wave bridge rectifier This type of rectifier has four termi nals two AC and a DC positive and DC negative Nothing is connected to the DC negative in this generator A rectifier may be...

Page 9: ...olders 10 Check output voltage with sensitive meter If very low i e 1 2 volt flash fields with a 12 VDC battery Output voltage too high Engine speed too high See engine manual Generator overheating 1 Generator overloaded 2 Armature rubbing pole shoes 3 Poor ventilation 4 Short circuit in fields 5 Short turns in armature 1 Reduce load 2 Check bearing condition Check field shell bearing bracket alig...

Page 10: ... 60928 000 1 Cover Plate 12 61687 000 1 Field Shell Coil Assy 13 60925 000 1 Upper Field Coil 14 60925 001 1 Lower Field Coil 15 60931 000 1 Receptacle Cover Plate 60931 001 1 Recpt Cove Plate UL Model 62170 000 1 Cover Plate 16 60960 000 2 Receptacle 17 91286 015 1 15 Amp Circuit Breaker 18 53976 000 1 Rectifier 19 59688 000 3 Barrier Spacer NI 23532 000 1 Spacer NI 41384 017 1 Copper Strap NI 40...

Page 11: ...11 12095 10 60706 230 WIRING DIAGRAM 2FS WITH Q WINDING WIRING DIAGRAM 2FS WITHOUT Q WINDING ...

Page 12: ...to 12 months from date of purchase In no event is WINCO liable for incidental or consequential damages Note Some states do not allow limitation on the duration of implied warranty and some states do not allow the exclusion or limitation of incidental or consequential damages so the above limitations may not apply in every instance This warranty gives you specific legal rights which may vary from s...

Reviews: