6  Commissioning 

  Before  putting  into  operation,  the  entire  system  should  be  flushed  through.  Particles  in  the  system  compromise  the 

operating reliability.  

  Fill the heating system slowly with water and vent all the air. 

  Start-up the heating system. 

  While the System is heating up, water will leak out of the safety valve.

 

 

Before  the  handover  of  the  system  to  the  end  user/owner,  the  plumbing  contractor  should  ensure  that  the 
system is tested to full load, controls are set and that pipe work and connections are without leaks. 

Afterwards, 

the end user has to be instructed in the operation and handling of the tank, as well as the system. The instruction must 
to be documented in the installation and maintenance record.,

 

  Please note that the operation and lifetime of the system depend decisively on a regular maintenance.  

7  Maintenance and wear parts 

Regular maintenance increases the lifetime and operation reliability of the system.  Decalcification at regular intervals may be 
necessary in highly calcareous water areas.  

Attention – only valid for heating tanks with hot water supply.

 

A  chemical  decalcification  can  be  carried  out  by  a  specialist  using  an  approved  decalcifier  and  taking  the  appropriate 
precautions. 
1. 

The safety valve protects the tank against excess pressure. The functional capacity must be checked at regular intervals 
by venting. If an expansion vessel is used, the safety valve is not, or only rarely, required. Over a longer period of time 
therefore, it can become blocked and not function when needed. 

2. 

If there is a danger of freezing, the DHW tank should be permanently heated or completely emptied. 

3. 

A  damp  cloth  is  sufficient  to  clean  the  outer  parts.  Please  avoid  using  any  abrasive  or  solvent  cleaning.

Summary of Contents for WPH 300

Page 1: ...nd maintenance record must be entirely completed and the user has to be instructed accordingly Efficient operation can only be guaranteed if the instructions of this manual are followed Warranty does...

Page 2: ...e longer than 2 m If for any compelling reasons 3 bends or a length up to 4 m are required then the entire exhaust line must be designed one nominal size larger More than 3 bends or a length exceeding...

Page 3: ...790 950 1905 1560 280 1560 280 1950 1480 940 280 WPH 980 790 950 2175 1830 280 1830 280 2200 1750 1060 280 WPH 1000 850 1010 1920 1590 280 1590 280 1980 1485 940 280 WPH 1500 1000 1160 2130 1710 340 1...

Page 4: ...with their application and supply medium Sensors and thermostats necessary for temperature control must be securely and permanently positioned on the tank immersion sleeve and sensor rail The tank s...

Page 5: ...operation and lifetime of the system depend decisively on a regular maintenance 7 Maintenance and wear parts Regular maintenance increases the lifetime and operation reliability of the system Decalci...

Page 6: ...O Duo 302 403 502 753 1000 1502 2002 5 20 27 WBO Basic Integral 302 5 20 27 WP Sol 302 403 502 750 5 20 27 WBO H 300 400 500 750 1000 5 20 27 WTL 120 150 200 300 5 20 27 GS 117 152 192 5 20 27 Wikosol...

Page 7: ...operation and maintenance Place Date Customer Installer Signature Signature Place of installation Name ZIP Code Place Street Phone Tank model Serial number Date of invoice In the case of reclamation t...

Reviews: