Connect the terminal on the lower right-hand side marked
with the international symbol a connector with a nominal
cross section <10 mm
2
. All the appliances installed and the
earth system of the building shall be connected like this.
Connection to waterworks
Water inlet pressure must be between 50 and 300 kPa,
otherwise install a pressure regulator on the line before
the appliance.
Install a cut-off valve for each supply on the line before
the appliance.
Water connections to 10 mm are fitted in the lower part on
the right-hand side of the appliance.
Make connections according to regulations currently in
force.
Commissioning and testing
Once all the connections have been made, the appliance
and the overall installation must be checked following the
directions given in this manual.
Check in particular:
- that the protective film has been removed from the ex-
ternal surfaces;
- that the lower front panel removed for the electrical con-
nection of the appliance has been fitted back into posi-
tion;
- that connections have been made in accordance with
the requirements and directions indicated in this ma-
nual;
- that all safety requirements in current standards, statu-
tory regulations and directives have been met;
- that the water connections are leak-free;
- that the electrical connection has been performed ac-
cording to standards.
In addition, check that once the appliance has been in-
stalled, the power cord is neither subject to stretch nor in
contact with nor surfaces.
Now proceed to light the appliance as directed in the in-
structions for use.
While the appliance is in use, voltage should not differ
from the nominal voltage more than +/- 10%.
The test report must be completed in full and submitted to
the customer who should then sign in acceptance. With
effect from this moment, the appliance is covered by the
manufacturer’s warranty.
Maintenance of the appliance
Warning! :
All maintenance operations shall only
be performed by a technically qualified service centre!
To ensure correct and safe operation, the appliance must
be inspected and serviced at least once a year only.
Maintenance includes also controlling the components
and tear of pipes, feeding pipes, electrical components
etc.
It is advisable to replace worn components during mainte-
nance operations to avoid the need for other maintenance
calls and unexpected failures.
It is also advisable to apply for a maintenance contract
with the customer.
Possible failures and their elimination
Warning! :
Only technically qualified service
centres can perform the operations described below!
Warning! :
Before resetting the safety thermo-
stat, it is always necessary to eliminate the problem