Installing the Sample Cylinder
SC Single Cavity Cylinder
15.
Ensure that the inlet and outlet valves on the SC are closed.
16.
Install the inlet valve of the SC to the cylinder hanger on the manifold (
Figure 1
).
17.
Installation is now complete.
Constant Pressure Cylinder
18.
Ensure that the pre-charge and product inlet valves on the constant pressure cylinder are closed.
19.
Tube from the pre-charge pressure supply to the pre-charge inlet valve on the constant pressure cylinder.
If the GSS-4PM is equipped with the standard probe and process gas will be used to pre-charge the constant pressure cylinder,
remove the plug from the probe base, and then tube from this port to the pre-charge valve on the constant pressure cylinder.
Welker recommends first installing a valve to the port on the probe base.
If the GSS-4PM is equipped with the optional LE-2SSKO and process gas will be used to pre-charge the constant pressure
cylinder, remove the plug from the back of the regulator, and then tube from this port to the pre-charge valve on the constant
pressure cylinder.
If the optional auxiliary instrument air supply will be used to pre-charge the constant pressure cylinder, remove the plug from
the back of the regulator, and then tube from this port to the pre-charge valve on the constant pressure cylinder.
20.
Tube from the sample outlet on the base of the GSS-4 to the product inlet valve on the constant pressure cylinder.
21.
Pre-charge the constant pressure cylinder. Refer to the
Installation, Operation, and Maintenance
(IOM)
Manual
for the
constant pressure cylinder for instructions on pre-charging the constant pressure cylinder.
12
IOM-022
MODEL: GSS-4PM
REV: F
13839 West Bellfort Street, Sugar Land, TX 77498
welker.com