5. Commissioning information
5.1
Water connection (piping)
The hot and cold water pipes must be laid in the equipment room
before the Sanoasa Wellness Multicentre steam shower is assem-
bled (see the installation plan for hot and cold water in the appen-
dix to the operating instructions – Special information – for more
on this). Before the water-carrying pipes are connected, they must
be rinsed to prevent the ingress of chips and other contaminants
Overview of the pipework
1. Lead steam generator:
400 V 3/N/PE 6.6KW 3 x16A
Alternativ: 230V 3x6 mm
2
1/N/PE 32A 6.6KW
(This optional connection possibility must be ordered.)
2. Home electricity supply, 230V 1/N/PE 10A
3. Hot water supply, ¾ inch outside thread
4. Cold water supply, ¾ inch outside thread
5. Connection steam generator, drainage
6. Connection for cold water to steam generator
7. Connection for hot water to shower panel
8. Connection to steam extrusion outlet
9. Connection for cold water to shower panel
10. Connection steam lead
11. Filling supports for decalcification
12. Connection temperature feeler
13. Light switch see points 34 to 36
14. Steam generator control (see technical documentation
Sanaosa Home, page 8/9)
15. Connection hand nozzle
16. Connections side nozzles for shower panel
(4 side nozzles are standard)
17. Side nozzles in-wall valve
18. I-box thermostat
19. Trio Stop adjustable valve deluge/hand nozzle
20. Connection deluge nozzle
21. Door fastening point
22. Leads for light and music technology
23. Drilling area for the shower bar fastening
into the steam generator system, which could lead to damage.
The entire water-carrying system must be subjected to a pressure
and leak test by trained specialists before sealing, tiling and com-
missioning. The pressure test must be documented and the report
delivered to the operator.