Switch-Over Automatic, type UMAP NT35-R
Index: 03
Date modified: 28/03/2022
OI No.: BA SW 017-03 Umschaltautomatik Typ UMAP NT35-R EN.docx
Page 8 of 14
4
Installation / Commissioning / Operation
4.1
Select the installation site
The following should be observed in regard to the installation site:
a)
A freely accessible installation site should be selected to facilitate operation and subsequent maintenance
tasks.
b)
Protection tubs must be available for the chemical containers.
c)
Observe the temperature specifications for the surrounding air and medium in accordance with
Chapter
. No flammable vapours, dust or gases may be present in the immediate vicinity of the
device. A floor drain is recommended.
d)
The device must not be exposed to the elements. It may not be installed outdoors. The system must be
protected from frost and direct sunlight.
e)
An isolated ground socket is required.
f)
The installation site must comply with the accident prevention regulations (Germany BGR-GUV-R 108)
and should not be accessible to unauthorised persons. A separate storage room must be available for
stocking the chemicals.
g)
It must be possible to vent and aerate technical areas so that hazardous substances do not occur in
health-hazardous concentrations (from accident prevention regulations BGR-GUV-R 108).
h)
A pump for dosing the chemical must be available on site or must be ordered separately. Pay attention
to the durability of the pump materials!
4.2
Installation instructions / installation
The “switch-over automatic” is preinstalled on a mounting plate and is delivered ready to plug in. The
device must be supplied with continuous voltage.
a)
Mount the device in a suitable location in the technical room using 4 screws.
b)
Mount the external dosing pump in a suitable location, for example next to the mounting plate.
c)
Attach warning and notice signs in accordance with the locally applicable accident prevention
regulations (Germany: BGR-GUV-R 108) at the designated positions.
In particular for the labelling of
the chemicals used!
4.3
Commissioning
When using a peristaltic pump
a)
Venting of the peristaltic pump is not necessary. The type of pump to be used must already be taken
into account when ordering.
a)
Place the containers under the switch-over automatic in suitable collecting tubs and open them.
Ensure
that the correct chemical is used!
b)
Place the suction sets in the containers and lightly screw on the lids
c)
Plug in the switch-over automatic;
caution, the dosing pump may start!
After a power failure, suction continues at the most recently activated container.
When using a solenoid diaphragm pump
a)
Solenoid diaphragm pumps
must always be vented on the suction side
. The type of pump to be used
must already be taken into account when ordering.
b)
Place the containers under the switch-over automatic in suitable collecting tubs and open them.
Ensure
that the correct chemical is used!
c)
Place the suction sets in the containers and lightly screw on the lids
d)
Connect the suction line of the dosing pump to the outflow of the switchover valve and the return line
to the pump’s ventilator.
e)
Install the on-site suction ventilator and ventilate with a manual vacuum pump until the
suction ventilator is ¾ full.
f)
Keep the dosing pump running
g)
Check if the suction hose from the suction ventilator to the pump and the pump head are
completely vented (pump head must fill with liquid). The pump is now vented. The dosing
hose from the pump to the injection point does not need to be vented.
h)
Plug in the switch-over automatic;
caution, the dosing pump may start!
After a power failure, suction continues at the most recently activated container.