Membrane replacement: Performed every year after the first year in service.
Annual PM Procedures:
Follow quarterly PM procedures as described above.
1.
Remove top and front panels
2.
Remove 3 prefilters and post calcite feeders (
DO NOT REPALACE WITH
NEW FILTERS AT THIS TIME)
3.
Remove 3 Reverse Osmosis Membranes (figure 5)
4.
Replace with new membranes provided in PM kit #501020
5.
Replace 3 prefilters and PH Balancer. Installing these filters will turn the water
supply on to the unit and start production of water.
Figure 4
Figure 5
Figure 6
Remove eight screws from front panel. Remove front panel. Remove first stage filter to
shut down incoming water flow to system. Drain the tank of boiler feed water by
performing a blow down on the boiler. After tank has been completely drained,
disconnect the membranes by pressing in on the collets around the colored tubing (figure
6) to the membrane and pull. Each membrane should be removed one at a time insuring
proper placement of tubing in corresponding color coded ports. Re-tighten first stage
filter to start water flow, listen for permeate pumps to begin pulsating and check for leaks
then secure panel.
By passing the unit:
The HS-200 unit can be placed into by pass if for some reason the equipment has failed
and or has clogged filters. To by pass the RO system, open top panel by removing eight
screws (figure 7)and open ½” brass “Watts” ball valve (figure 8) for tap water by-pass.
After service has been achieved close the “Watts” ball valve and wait for the system to
begin permeating.
Figure 7 Figure 8