Testing After Installation
2
Use the illustration and instructions to adjust the
packing after installing the pump into the apparatus.
Note:
Certain parts have been removed from the
illustration to provide a clear view of the
equipment being tested.
1 Operate the pump at its maximum intended
pressure for 10 minutes.
2 Observe the drip rate. Optimal leakage is 10
to 120 drops per minute. Maintaining this rate
facilitates the cooling of the packing.
3 If the drip rate is too high, turn off the
pump and gradually tighten the gland nuts,
alternating between them to make sure that
the gland stays level.
4 Operate the pump at its maximum intended
pressure for 2 minutes. Observe the drip rate,
then repeat the previous step until leakage is
within the optimal range.
5 Repeat the process with the packing housing
at the other end of the pump.
6 Make sure that you perform all tests required
by the National Fire Protection Association.
Summary of Contents for CP-4
Page 2: ......
Page 20: ...Notes ...
Page 22: ...22 41 Safety Introduction Disassembly Assembly Impeller Shaft Assembly ...
Page 28: ...28 41 Safety Introduction Disassembly Assembly Pump Body Assembly ...
Page 40: ...Notes ...