Installing Ground Sleeves

Dig a 15” minimum diameter hole 3’1” deep in either the soil or existing concrete pad. Put in a 3” gravel base to allow for 

water drainage.

For Standard Ground Sleeves:

Place the ground sleeve into the hole, making sure the top of the ground sleeve is a minimum of 6” above the finish grade. 

Level and brace the ground sleeve, pour in concrete, and allow to set for at least 72 hours.

For Flush Mounted Ground Sleeves:

Place the ground sleeve into the hole, making sure the top of the lower section is set flush with the finish grade. Bolt the top 

section to lower section with the included bolts. Level and brace the ground sleeve, pour in concrete, and allow to set for at 

least 72 hours. When unit is not in use, remove top section and replace with center plate. 

Finish
Grade

3/8” - 16 x 5” 
Nut and Bolt 

(2 Required)

Top section attaches to lower section

Center plate is used to cover lower section when 
umbrella is not being used.

Lower section is permanently installed into soil 

or existing concrete pad. (see Installing Ground 
Sleeve instructions above)

6”

2’ 10”

Finish
Grade

Ground Sleeves

Installation Instructions

www.waterlootent.com            1-800-537-1193 

       3105 Airport Blvd. Waterloo IA, 50703

Summary of Contents for Permabrella

Page 1: ...1 3 8 Slef Locking Nuts 14 8 IMPORTANT Consult a local utility company prior to installation Proper installation and site conditions are the responibility of the installer Check for any obstacles prior to site preparation Permabrella Installation Instructions WWW WATERLOOTENT COM 1 800 537 1193 3105 Airport Blvd Waterloo IA 50703 MANPOWER REQUIRED Two installers are required to install both top an...

Page 2: ...the lower section is set flush with the finish grade Bolt the top section to lower section with the included bolts Level and brace the ground sleeve pour in concrete and allow to set for at least 72 hours When unit is not in use remove top section and replace with center plate Finish Grade 3 8 16 x 5 Nut and Bolt 2 Required Top section attaches to lower section Center plate is used to cover lower ...

Page 3: ...ace is centered between the ears on the bow and the hooks on the bow and brace are both facing the same direction 4 From the ground place the hook end of the brace into the lower casting making sure it is secured on the ring Grasp the outside end of the bow and slowly raise the bow until the hook is aligned with upper casting Repeat procedure until all bows and braces are attached Make sure each b...

Page 4: ...ng is approximately 1 0 above the hole for the safety pin Do not over crank Insert safety pin attached to the lower casting and remove the winch handle 8 To lower umbrella remove safety pin Turn winch handle counter clockwise and lower uit slowly until the lower casting is 6 8 inches above the face plate Remove the winch handle Over cranking in either direction may cause the cable to become crimpe...

Reviews: