4
STEP 4SS
— Use UP or DOWN buttons to switch
between:
• 1-99 Days, or
• 7-Days Between Regenerations
Press SET HOUR button to go to Step 5SS.
STEP 5SS
— Use UP or DOWN buttons to switch
between 60 Hz or 50 Hz option. Supply your own
transformer if using 50 Hz option.
Press SET HOUR button to go to Step 6SS.
STEP 6SS
— If a differential pressure switch is
installed and actuated:
• a regeneration will occur immediately if no arrow
points at Regen Hour; or
• a regeneration will occur at the delayed
regeneration hour if an arrow points at Regen Hour.
Use UP or DOWN buttons to switch between the
two choices. If a differential switch is not installed
the settings in this display are ignored. Press SET
HOUR to exit
SYSTEM SETUP
.
NOTE:
The two terminals at “A”, if connected to an external pressure differential switch or other “dry” contact
switch which closes for five minutes, can be used to initiate an immediate backwash or a backwash scheduled for
the next regeneration time. The choice is determined in Step 6SS above. If no connection is made at “A” it
doesn’t matter what setting is made in 6SS. The backwash will occur according to the days between
regenerations and the time of regeneration settings.
A. Differential pressure switch or other external “dry” switch connection
B. Motor wire connection shown for reference only
C. Transformer wire connection shown for reference only
A
B
C