1.)

TENT LOCATION................................................................................................

2

2.)

PARTS LIST 

....................................................................................................... 3

3.)

FRAME ASSEMBLY

........................................................................................ 4-5

Post & Centrepole Assembly .................. Step 2....................... PAGE

4

Upper Frame Assembly  ......................... Step 3....................... PAGE

4

Cross Cable Installation  ......................... Step 4 & 5 ................ PAGE

4

Cable: Slide Wall Installation (optional) .. Step 6....................... PAGE

5

4.)

TENT TOP INSTALLATION

................................................................................. 5

Protecting Tent Top ................................. Step 7....................... PAGE

5

Unfolding Tent Top  ................................. Step 8 ...................... PAGE 

5

Securing Tent Top to Frame ................... Step 8A/8B .............. PAGE

5

5.)

ERECTING THE TENT 

................................................................................... 6-7

Installing Posts  ....................................... Step 9 ...................... PAGE

6

Installing Centrepole ............................... Step 10 - 11.............. PAGE

6

Securing the Structure  ........................... Step 12 .................... PAGE

7

6.)

GUY ROPE INSTALLATION

............................................................................... 7

7.

)

WALL INSTALLATION

......................................................................................... 8

8.)

JOINER INSTALLATION 

.................................................................................... 9

9.)

SUMMARY

........................................................................................................ 10

10.)

CARE FOR YOUR VINYL TOPS 

..................................................................... 11

11.)

MAINTENANCE

............................................................................................... 11

Tent Location

VERY IMPORTANT!
Ascertain tops, guys, and other tent parts are in good operating condition. Any

components showing damage should be replaced immediately.

Before unloading, review the proposed location of the tent. In doing so, take into

account the following:

Hazards

Locate, mark, and avoid any overhead or underground electrical, phone, gas,
sprinkler or other lines. Take note and always be aware of any and all hazards. DO
NOT BEGIN ANY ASSEMBLY UNTIL THE HAZARDS HAVE BEEN MARKED AND
CAN BE SAFELY AVOIDED.

Access

Plan the best route for bringing the tent and equipment for the setup onto and off
the site.

Drainage

Attempt to influence the location of the tent so that rain or melting snow can drain
away.

Obstacles

A clean, level and unobstructed site will provide an easy assembly of the tents.

Weather

Do not attempt to setup the tent during thunderstorms, high winds or other extreme
conditions.

Safety

Before the set up, instruct the crew on safety procedures. All local safety and fire
regulations must be followed.

ALL SITE PERSONNEL MUST FOLLOW OCCUPATIONAL HEALTH AND SAFETY PROCEDURES.

PAGES

..\graphicshome\marquee\manuals\MQ 20\MQ20H Manual 2009.pdf

Summary of Contents for MQ20H

Page 1: ...tent is recommended before weather becomes extreme A successful event is a safe event 3 Proper safety equipment such as hard hats steel toe shoes and safety glasses should be used to ensure a safe se...

Page 2: ...ould be replaced immediately Before unloading review the proposed location of the tent In doing so take into account the following Hazards Locate mark and avoid any overhead or underground electrical...

Page 3: ...161 7 MIDJOINT 4 10667 7284 8 CENTREPOLE ASSY 1 10978 11544 9 BOLT 5 16 3 NC 4 4093 10 NUT 5 16 NYLOK 4 8369 11 LOCK PIN 5 7843 1 TENT TOP 1 10977 12 STAKE 3 4 34 8 10666 13 FLAG POLE EXT 1 9523 14 DR...

Page 4: ...t loop lift last corner to shorten the distance between corners and hook the cable over the pin Lowering the corner causes the corners to adjust their position and the cables to tighten 5 Top Cable Bo...

Page 5: ...ding Walls are to be installed attach the Cable for Slide Wall 20 to the Corners and tighten turnbuckle Step 7 Unfold Drop Sheet not included 19 over the Cross Cables to protect the Tent Top and to ke...

Page 6: ...both cables directly below the Centrepole sleeve Secure the Centrepole to the cables using the Lock Pin Top Cross Cable Bottom Cross Cable Step 9 Lock post in place using lock pins 10 INSTALLING POST...

Page 7: ...curing method Site conditions may require guying and or anchorage different from what was provided with the structure Remove Drop Sheet and fold up keeping clean side in 1 2 3 4 5 graphicshome marquee...

Page 8: ...allation Before installing walls make sure toggle ropes are evenly tensioned and the Tent Top is evenly positioned on the frame Check that Cable for Slide Wall is properly tensioned Tighten with turnb...

Page 9: ...in the adjacent tent 3 Attach clips to Cable Slide Wall 5 Insert lapels between two posts Loosen toggle ropes to slip lapels underneath it 6 Spread lapels under valance 7 Insert the strap on the lapel...

Page 10: ...6 Attach Tent Top webbings to corner loops 7 Install two Posts Secure with Lock Pin and insert the s hook of the toggle rope into the hole in the Post Base 8 Move Drop Sheet to clear the Cross Cable...

Page 11: ...cally the fabric should be cleaned in place or when dismantled Using mild detergent water and a deck mop clean wipe the fabric roof or walls Let dry Repair any damage to the fabric using a WSSL Fabric...

Page 12: ...licable building code The WSSL Tent C Can For its 40 years anniversary Warner Shelter Systems Limited WSSL offers to the world with a NEW Warner Innovation WSSL Garage come complete with galvanized st...