Maintenance
5.1
Periodic Maintenance Schedule
The table below lists basic machine maintenance. Tasks designated
with check marks may be performed by the operator. Tasks
designated with square bullet points require special training and
equipment.
(1)
If the insulation resistance has become noticeably lower than the previous inspection, an inspection of the motor
will be necessary.
(2)
See Inspecting Lubricant and Replacing Lubricant in this section.
(3)
Specialized know-how is required for inspecting and replacing the mechanical seal. Consult with your nearest
dealer or Wacker Neuson representative.
(4)
Consult with your nearest dealer or Wacker Neuson representative regarding overhauls.
Pump
Weekly
Monthly
Every
1000
hrs.
Every
2000
hrs.
Measure insulation resistance.
Reference insulation resistance =
1M
Ω
or greater.
(1)
Measure operating current.
Compare with rated current.
Measure supply voltage.
Compare with allowable range (within ±5% of rated voltage).
Pump inspection.
A noticeable drop in performance may indicate wear in the
impeller, etc., or else clogging of the strainer, etc. Remove the
clogged debris and replace any worn parts.
Lubricant inspection.
Change lubricant.
Designated lubricant: SAE 10W/20W.
(2)
Change mechanical seal.
(3)
Overhaul.
This should be carried out even if there are no problems with
the pump. The frequency depends on how continuously the
pump is in use.
(4)
Summary of Contents for PSA2 500
Page 29: ...PS2 500 PSA2 500 Maintenance wc_tx001357gb fm 29 11 10 12 9 8 7 6 1 2 3 4 wc_gr001206...
Page 54: ...AEM Safety Manual AEM Safety chapter pump fm 54...
Page 56: ......
Page 58: ......
Page 60: ......