INSTALLATION OPERATIONS AND MAINTENANCE MANUAL - VORT NRG MEGA-R SERIES
16.4 Detail of electrical panel
17. STARTUP
17.1 Preliminary checks
It is necessary to carry out preliminary checks on the electrical and hydraulic parts before starting the unit.
Perform the commissioning operations in accordance with all the requirements of the previous paragraphs.
Malfunctions or damage may also result from lack of proper care during shipment and installation. It is good
practice to check before installation or commissioning that there are no damages due to tampering, vibration
during transport, mistreatment suffered on site.
• Check that the machine is installed in a state of the art manner and in accordance with the instructions in this manual.
• Check electrical connection and correct fastening of all terminals.
• Check that the voltage is as indicated on the unit's rating plate.
• Check that the unit is connected to the earth system.
• Check that there are no leakages.
• Check that the hydraulic connections have been installed correctly and that all indications on the nameplate are respected.
• Check that the system has been properly vented.
• Check that fluid temperatures are within operating limits.
• Before turning the unit on, check that all closing panels are in place and secured with the appropriate screws.
Do not modify the internal electrical connections as this will immediately invalidate the warranty.
MAIN BOX
MAIN
POWER SUPPLY
LINE
HEATERS' KIT
BOX
triac signal
sectioning
triad
MAINSWITCH
DOUBLE BOX WITH SINGLE DOOR INTERLOCKED BY
HEATERS' KIT MAINSWITCH