20 / 36
eco-DUO330
4.1.7
Calibration
To obtain a precise dosing result, the dosing quantity must be calibrated. This is performed
using the eco-CONTROL EC200 DUO dosing control unit. The exact procedure can be found
in the dosing control unit manual.
4.2
Switching on, starting dosing process
Daily at the start of the shift / when starting work, perform the activities as described in
Section 5.1 “Maintenance intervals” (page 24).
Start supply of material to the dispenser.
If present, remove cover.
Switch on the dosing control unit.
Dose the individual components (in manual operation) from the mixing head without static
mixer. Use the calibration adapter (35) for this.
Check whether both components escape without bubbles and that the outlet opening are not
blocked or stuck together.
Check the dosing quantity of each of the two components in order to guarantee a consistent
dosing result. If there are deviations, dosing must be calibrated. The exact procedure can be
found in the dosing control unit manual. The result of the check must be recorded together
A calibration adapter (35) is available for calibrating
the dispenser. It is mounted on the outlet openings.
Remove the static mixer.
Unscrew the screws (9) in the locking plate (11).
Mount the calibration adapter (35).
Perform calibration according to the dosing
control unit operation manual.
Dismantle the calibration adapter (35).
Tighten the screws (9) and locking plate (11).
Position the static mixer.
NOTE
The supply of material to the dispenser must be ensured before dosing starts.
Dry running may destroy the stator.
Fig. 10
35
11
9
9