5.6 Preventive maintenance procedures
5.6.1 Switch on
Perform the following steps:
1. Turn on the water supply.
2. Connect the power cord to the power mains socket.
3.
(on page 46).
4. Switch the
[ON/OFF]
power switch to the
ON
position.
▪
check the inside view drawing (see on page 17) for the
precise location.
5.
(on page 46).
6. The coffee machine will start up.
7. The main screen is displayed with the message 'filling boiler'
and then 'heating boilers' in the message area (see on page
21) on the screen.
NOTE
If the door was left open for too long the service menu
is shown.
Tap the
[Exit]
button and then the
[Close door and
press here to quit service]
button to leave the
Service
menu.
8. After a few minutes the message 'heating boilers' disappears
and the machine is ready for use.
5.6.2 Open the door
Perform the following steps:
1. Insert the
key
in the lock of the door of the coffee machine.
2. Turn the
key
90 degrees clockwise.
3. Open the door.
▪
The
Service
menu is displayed on the screen.
NOTE
Do not leave the door open unattended to prevent
unauthorized access to the inside of the machine.
5.6.3 Close the door
Perform the following steps:
1. Insert the
key
in the lock of the door of the coffee machine.
Virtu CEC Medium Cabinet 70/90 CoEx® brewer User Manual 5DUCEK20M EN V2.0