23
Commissioning steps
Inspection steps
Maintenance steps
Page
•
................................................................................................. 24
•
•
•
2. Checking all connections on the heating water side for leaks
•
3. Switching on the power and starting the commissioning sequence
............................ 25
•
•
5. Loading the standard setting
............................................................................................ 25
•
•
•
•
•
•
8. Selecting a burner / an additional boiler
.......................................................................... 25
•
•
9. Selecting the connection for heating circuits 1 to 3
....................................................... 26
•
•
10. Selecting the DHW connection
......................................................................................... 26
•
•
11. Solar connection
•
•
12. Changing the heating circuit designations
...................................................................... 26
•
13. Checking outputs and actuators
...................................................................................... 26
•
•
14. Lambda probe
•
•
•
16. Displaying the menu structure
.......................................................................................... 28
•
17. Matching the control unit to the heating system
............................................................ 28
•
18. Adjusting the heating curves
............................................................................................ 28
•
19. Heating up
•
•
................................................................................................. 30
•
•
•
21. Checking the function of the safety valves
•
•
•
22. Checking the function of the thermally activated safety valve
...................................... 31
•
•
•
23. Checking the installation room ventilation air aperture
•
•
24. Test run
•
25. Instructing the system user
.............................................................................................. 31
•
26. Maintenance and cleaning intervals
................................................................................. 31
•
27. Cleaning and calibrating the Lambda probe
................................................................... 33
•
•
•
29. Checking gaskets
Commissioning, inspection, maintenance
Steps - commissioning, inspection and maintenance
5684984