29
Commissioning steps
Inspection steps
Maintenance steps
Page
•
............................................................................................... 30
•
•
................................................................................................. 32
•
•
•
3. Checking all connections on the heating water and DHW sides for leaks
•
............................................................................................... 34
•
•
•
•
•
•
•
7. Checking the static pressure and supply pressure
........................................................ 36
•
8. Function sequence and possible faults
........................................................................... 37
•
9. Setting the maximum heating output
............................................................................... 38
•
•
10. Performing an actuator test
.............................................................................................. 38
•
11. Adjusting pump rate of integral circulation pump
.......................................................... 38
•
12. Leak test on balanced flue system (annular gap check)
................................................ 40
•
13. Burner adjustment when connecting multiple flues to a shared flue system
•
•
•
15. Checking the burner gasket and burner gauze assembly
.............................................. 42
•
•
16. Checking and adjusting the ignition and ionisation electrodes
.................................... 43
•
•
17. Checking the back draught safety devices
...................................................................... 43
•
18. Cleaning the heating surfaces
.......................................................................................... 44
•
•
19. Checking the condensate drain and cleaning the trap
................................................... 44
•
•
•
•
21. Checking the neutralising system (if installed)
•
22. Checking the flow limiter (only for gas condensing combi boiler)
............................... 47
•
•
•
23. Checking the expansion vessel and system pressure
................................................... 47
•
•
•
24. Checking the safety valve function
•
•
•
25. Checking the electrical connections for firm seating
..................................................... 48
•
•
•
26. Checking all gas equipment for leaks at operating pressure
........................................ 48
•
•
•
•
•
28. Checking the combustion quality
..................................................................................... 49
•
•
•
29. Checking the flue system for unrestricted flow and leaks
•
30. Matching the control unit to the heating system
............................................................ 50
•
31. Adjusting the heating curves
............................................................................................ 50
•
32. Instructing the system user
.............................................................................................. 50
Commissioning, inspection, maintenance
Steps - commissioning, inspection and maintenance
6173886