3.2.Requirements for chimney
-
The chimney, the flue and the air ducts should meet construction standards and rules.
-
The inlet into the chimney must be as short as possible and must be directed
upwards. The total length of the inlet must not exceed 2 m. The pipe must be secured in
place with the help of a clamp;
-
The diameter of the chimney must be at least 150 mm;
-
This opening must be free of any other additional connections working
contemporaneously;
-
If the chimney is connected with an additional bend, it's diameter must be at least as
the diameter of the chimney of the heater;
-
Connection points and inlets into the chimney must be sealed properly.
3.3.Requirements for connection of a water heating
tank: (Provided that a heat exchanger is installed).
-
For the connection of the heat exchanger to the open water heating tank steel pipes
should be used, the diameter of the pipes must be at least ¾”;
-
No closing devices may be installed between the heater and the tank;
-
The tank cover must have a pipe (Pic. 4, pos. 5) or an opening to release the build-
up pressure when the water is heating;
-
Recommended volume of the tank is 50 ÷ 100 l.
In case there is a possibility for water to freeze when the sauna is not in use, the water must
be released. For this purpose a valve for releasing water (pos. 6) should be installed at the
lowest point of the system.