Carry out the pressing process.
Open and remove the press jaw.
ð
Connection is pressed.
3.2.4
Leakage test
The installer must perform a leakage test before commissioning.
Carry out this test on a system that is finished but not covered yet.
Comply with the general rules of engineering and the applicable direc‐
tives, see
„Regulations from section: Leakage test“ on page 8
Perform leakage test should in acc. with the general rules of engineering
for non-potable water installations.
Document the result.
3.3
Maintenance
NOTICE!
Inform your customer or the operator of the potable water
installation that the system has to be maintained on a reg‐
ular basis.
Observe the applicable regulations for the operation and maintenance
of potable water installations, see
„Regulations from section: Mainte‐
Viega recommends actuating the fitting regularly and
checking its function.
Handling
Easytop ball valve with SC-Contur
20 from 21