The installation of the LIN-300 ABS protection box involves two main steps:
1. Preparing the holes for the connectors;
2. Fastening the protection box.
3.1.5 Preparing the holes for the liquidtight connectors
1. To prevent damage, remove the LIN conditioner
before drilling the protection box. Do not misplace
the anti-vibration rubber mounts added to the
mounting brackets.
Before deciding on the location for the holes, make
sure that the liquidtight connectors will not be too
close to the LIN conditioner once it is reinstalled,
and that the cables will not be kinked.
Figure 4 : Suggested location for liquidtight connector holes
2. Drill holes and install the the liquidtight connectors.
Figure 5 : “Mounting the liquidtight
connectors on ABS protection box”
Figure 5 : Mounting the liquidtight connectors on ABS protection box
1.19'' [30mm]
1.19'' [30mm]
SIDE A
SIDE A
CL
Hole:1 1/8''[28.5mm]